Celebratory Milestones#

Provenance#

This document was generated based on the contents of the lsst-dm/milestones repository, version cd818df9, dated 2024-03-26. This corresponds to the status recorded in the project controls system for March 2024. This compares to February 2024.

Key milestones#

Code

Name

Due

Previously

A1570

Dome Structure enclosed

2022-11-30

Completed

T&SC-5600-9380

Demonstration of CCW control using CSC (Tekniker) - Complete

2023-02-01

Completed

T&SC-5600-9499

Begin TMA Vendor final performance Testing

2023-03-20

Completed

T&SC-5600-9445

Start TMA Science verification (Tekniker/UTE)

2023-03-27

Completed

T&SC-5500-1200

Beneficial Occupancy of Telescope Mount

2023-04-28

Completed

T&SC-6800-1463

Atmospheric Telescope Ready at Summit

2023-05-31

Completed

T&SC-6800-4190

AuxTel Vent Gates upgrade complete

2023-05-31

Completed

T&SC-5600-9090

MCS & IS integration and verification - Complete

2023-05-31

Completed

SUMMIT-3013

NEED: Pathfinder in ComCam on TMA

2023-06-30

Completed

A9290

Provisional dome rotation deCommissioning

2024-01-19

Completed

T&SC-5400-6300

Dome Ready For TMA Science Verification

2024-02-01

Completed

A9300a

Installation of Az Pinion & Gear completed

2024-03-01

2024-03-01

SITCOM-105

ComCam + PF re-Installed on TMA

2024-03-04

2024-03-04

SUMMIT-2975

LSSTCam Pre-Ship Acceptance

2024-05-07

2024-05-07

SUMMIT-2976

LSSTCam Received @ Summit

2024-05-22

2024-05-22

A9370

Calibration Screen Installation complete

2024-06-24

2024-06-24

A9360

Light Baffle installation Complete

2024-07-08

2024-07-08

SUMMIT-3056

COMP: Camera Reverification Complete

2024-10-02

2024-10-15

SITCOM-125

LSSTCam reverification complete

2024-10-02

2024-10-15

SITCOM-123

LSSTCam Installed on TMA

2024-11-14

2024-11-27

A9410

Installation of Light Windscreen Complete

2024-12-16

2024-12-16

SITCOM-XXX

Camera Ready for Engineering Punchlist Resolution

2025-01-01

2025-01-14

New1135

LSSTCam Cold

2025-01-01

2025-01-14

New1110

Full focal plane readout complete

2025-01-24

2025-02-06

SUMMIT-3023

COMP: TMA Refrigeration Tests Complete

2025-01-29

2025-01-29

COMC-0654-1000

COMP: Calibration Products Production Verified

2025-06-19

2025-07-02

A public HTML version for embedding is here.

Block Schedule

Download the PDF of this Block Schedule here.

Acronym

Description

AI

Artificial Intelligence

AI&T

Assembly Integration & Test

AP

Alert Production

CCW

Camera Cable Wrap

COMP

COMPlete

ComCam

The commissioning camera is a single-raft, 9-CCD camera that will be installed in LSST during commissioning, before the final camera is ready.

DM

Data Management

EPO

Education and Public Outreach

HTML

HyperText Markup Language

LDM

LSST Data Management (Document Handle)

LSST

Legacy Survey of Space and Time (formerly Large Synoptic Survey Telescope)

M1M3

Primary Mirror Tertiary Mirror

M2

Secondary Mirror

OCS

Observatory Control System

PDF

Portable Document Format

SC

System Commissioning

SITCOM

System Integration, Test and Commissioning

SLAC

SLAC National Accelerator Laboratory

SSP

Solar System Processing

SV

Science Validation

TCS

Telescope Control System

TMA

Telescope Mount Assembly