Provenance¶
This document was generated based on the contents of the lsst-dm/milestones repository, version 891695a5, dated 2022-08-13. This corresponds to the status recorded in the project controls system for July 2022.
Top milestones¶
- 2022-09-30 : EPO Construction Finish (EPOC285)
 - 2022-10-10 : TMA Contract Complete (T&SC-1404-0750)
 - 2023-03-28 : Dome Complete (T&SC-0400-0950)
 - 2023-04-27 : COMP: Camera Pre-Ship Review at SLAC (CAMM8090)
 - 2023-05-25 : 3-Mirror Optical System Ready for Testing (T&SC-1100-0400)
 - 2023-07-21 : Engineering First Light w/ComCam (LSST-1513)
 - 2023-10-13 : Camera Ready for Full System AI&T (COMC-060200-20930)
 - 2024-03-14 : System First Light (LSST-1520)
 - 2024-07-10 : Test report: Final Pipelines Delivery (LDM-503-17a)
 - 2024-07-10 : Mini-Survey 2 Complete (COMC-0654-0430)
 - 2024-07-17 : Operation Readiness Review Complete (SITCOM-130)
 
A public HTML version for embedding is here.
Supporting milestones¶
- 2022-08-30 : COMP: Camera Ready for Verification Testing (ITC00475_COM)
 - 2022-09-30 : User Interfaces Complete (EPO-M6)
 - 2022-09-30 : Citizen Science Commissioning Project running via LSST infrastructure Complete (EPOC304)
 - 2022-10-24 : Camera support asmy w/ComCam+PF+Int#1+CCW Installed on Telescope (SITCOM-92)
 - 2022-10-24 : M2 Glass installed on Cell (SITCOM-104)
 - 2022-12-12 : M1M3 cell+Surrogate Dynamic Testing on TMA done (SITCOM-97)
 - 2023-01-05 : M2 Installed on Telescope (T&SC-1100-0300)
 - 2023-01-18 : ComCam + PF re-Installed on TMA (SITCOM-105)
 - 2023-01-25 : TMA safe for transition to M1M3 glass mirror (SITCOM-102)
 - 2023-05-22 : LSSTCam Received @ Summit (SUMMIT-2976)
 - 2023-05-25 : M1M3 installed on the TMA (SITCOM-110)
 - 2023-06-30 : COMP: TMA Refrigeration Tests Complete (SUMMIT-3023)
 - 2023-07-03 : Ops rehearsal for data release processing #1 (ComCam data) (LDM-503-13)
 - 2023-09-15 : Optical testing on TMA complete (SITCOM-116)
 - 2023-10-13 : LSSTCam reverification complete (SITCOM-125)
 - 2023-10-17 : M2 coating decision (SITCOM-127)
 - 2024-01-12 : LSSTCam Installed on TMA (SITCOM-123)
 - 2024-03-14 : Ops rehearsal for data release processing #3 (LDM-503-16)
 - 2024-03-14 : Solar System Processing pipeline available. (DM-AP-17)
 - 2024-04-19 : Begin Science Verification (COMC-0140)
 - 2024-07-10 : Full integration of the Alert Production system within the operational environment. (DM-AP-16)
 
| Acronym | Description | 
|---|---|
| AI | Artificial Intelligence | 
| AI&T | Assembly Integration & Test | 
| AP | Alert Production | 
| CCW | Camera Cable Wrap | 
| COMP | COMPlete | 
| ComCam | The commissioning camera is a single-raft, 9-CCD camera that will be installed in LSST during commissioning, before the final camera is ready. | 
| DM | Data Management | 
| EPO | Education and Public Outreach | 
| LDM | LSST Data Management (Document Handle) | 
| LSST | Legacy Survey of Space and Time (formerly Large Synoptic Survey Telescope) | 
| M1M3 | Primary Mirror Tertiary Mirror | 
| M2 | Secondary Mirror | 
| SC | Science Collaboration | 
| SITCOM | System Integration, Test and Commissioning | 
| SLAC | SLAC National Accelerator Laboratory | 
| TMA | Telescope Mount Assembly |