Due | Name |
---|---|
30-Sep-2022 | EPO Construction Finish |
10-Oct-2022 | TMA Contract Complete |
28-Mar-2023 | Dome Complete |
27-Apr-2023 | COMP: Camera Pre-Ship Review at SLAC |
25-May-2023 | 3-Mirror Optical System Ready for Testing |
21-Jul-2023 | Engineering First Light w/ComCam |
13-Oct-2023 | Camera Ready for Full System AI&T |
14-Mar-2024 | System First Light |
10-Jul-2024 | Test report: Final Pipelines Delivery |
10-Jul-2024 | Mini-Survey 2 Complete |
17-Jul-2024 | Operation Readiness Review Complete |
Using July 2022 project controls data.