DMTN-232

Celebratory Milestones#

Provenance#

This document was generated based on the contents of the lsst-dm/milestones repository, version 33a52223, dated 2024-10-04. This corresponds to the status recorded in the project controls system for August 2024. This compares to July 2024.

Key milestones#

Code

Name

Due

Previously

COMC-3010

M1M3 Lift Test

2024-02-02

Completed

COMC-3000

TMA Final Testing Begins

2024-02-08

Completed

COMC-3030

M1M3 Glass Lift Prep

2024-02-16

Completed

COMC-3020

Pathfinder Testing starts

2024-02-19

Completed

COMC-3040

M1M3 Glass Installed

2024-03-20

Completed

COMC-3050

TMA Final Testing Complete

2024-04-25

Completed

COMC-3060

M1M3 Coating Begins

2024-04-29

Completed

COMC-3090

LSSTCam Arrival Allowed

2024-04-29

Completed

COMC-3080

LSSTCam Pack and Transport

2024-05-10

Completed

SUMMIT-2976

LSSTCam Received @ Summit

2024-05-16

Completed

COMC-3070

ComCam Removed from TMA

2024-05-24

Completed

COMC-3110

M2 Cell Removed from TMA

2024-06-20

Completed

COMC-3120

M2 Glass Installed

2024-07-10

Completed

COMC-3130

M2 Glass on TMA

2024-07-25

Completed

COMC-3170

LSSTCam Reverification Start

2024-08-15

Completed

COMC-3140

ComCam Installed on TMA

2024-08-19

Completed

COMC-3150

M1M3 Glass on TMA

2024-11-12

2024-09-17

COMC-3160

ComCam First Photon

2024-11-12

2024-09-18

COMC-3200

LSSTCam Reverification End

2024-11-19

2024-10-22

COMC-3180

ComCam off Sky

2024-12-16

2024-11-12

COMC-3190

ComCam off TMA

2024-12-23

2024-11-19

COMC-3210

LSSTCam on Top End Assembly

2025-01-06

2024-12-03

COMC-3220

LSSTCam L3 Checkout Done

2025-01-20

2024-12-17

COMC-3230

LSSTCam on TMA

2025-02-04

2025-01-01

COMC-3240

TMA Aligned

2025-02-11

2025-01-08

COMC-3250

Rubin First Photon

2025-03-31

2025-02-25

COMC-3260

TMA Pointing Models Complete

2025-04-16

2025-03-13

COMC-3270

TMA AOS Ready

2025-05-14

2025-04-10

COMC-3280

Rubin First Light

2025-06-19

2025-05-16

COMC-3290

Rubin SV1 Start

2025-08-13

2025-07-10

COMC-3300

Rubin SV2 Start

2025-08-13

2025-07-10

COMC-3310

Rubin Eng Prep for OPS Start

2025-09-09

2025-08-06

COMC-3320

Rubin Operations Readiness Review

2025-09-16

2025-08-13

A public HTML version for embedding is here.

Block Schedule

Download the PDF of this Block Schedule here.

Acronym

Description

AI

Artificial Intelligence

AI&T

Assembly Integration & Test

AP

Alert Production

CCW

Camera Cable Wrap

COMP

COMPlete

ComCam

The commissioning camera is a single-raft, 9-CCD camera that will be installed in LSST during commissioning, before the final camera is ready.

DM

Data Management

EPO

Education and Public Outreach

HTML

HyperText Markup Language

LDM

LSST Data Management (Document Handle)

LSST

Legacy Survey of Space and Time (formerly Large Synoptic Survey Telescope)

M1M3

Primary Mirror Tertiary Mirror

M2

Secondary Mirror

OCS

Observatory Control System

PDF

Portable Document Format

SC

System Commissioning

SITCOM

System Integration, Test and Commissioning

SLAC

SLAC National Accelerator Laboratory

SSP

Solar System Processing

SV

Science Validation

TCS

Telescope Control System

TMA

Telescope Mount Assembly