Celebratory Milestones#
Provenance#
This document was generated based on the contents of the lsst-dm/milestones repository, version 68ce2bd2, dated 2024-08-06. This corresponds to the status recorded in the project controls system for June 2024. This compares to May 2024.
Key milestones#
Code |
Name |
Due |
Previously |
---|---|---|---|
COMC-3010 |
M1M3 Lift Test |
2024-02-02 |
Completed |
COMC-3000 |
TMA Final Testing Begins |
2024-02-08 |
Completed |
COMC-3030 |
M1M3 Glass Lift Prep |
2024-02-16 |
Completed |
COMC-3020 |
Pathfinder Testing starts |
2024-02-19 |
Completed |
COMC-3040 |
M1M3 Glass Installed |
2024-03-20 |
Completed |
COMC-3050 |
TMA Final Testing Complete |
2024-04-25 |
Completed |
COMC-3060 |
M1M3 Coating Begins |
2024-04-29 |
Completed |
COMC-3090 |
LSSTCam Arrival Allowed |
2024-04-29 |
Completed |
COMC-3080 |
LSSTCam Pack and Transport |
2024-05-10 |
Completed |
SUMMIT-2976 |
LSSTCam Received @ Summit |
2024-05-16 |
Completed |
COMC-3070 |
ComCam Removed from TMA |
2024-05-24 |
Completed |
COMC-3110 |
M2 Cell Removed from TMA |
2024-07-03 |
2024-06-07 |
COMC-3120 |
M2 Glass Installed |
2024-07-08 |
2024-06-28 |
COMC-3170 |
LSSTCam Reverification Start |
2024-07-15 |
2024-07-15 |
COMC-3130 |
M2 Glass on TMA |
2024-07-18 |
2024-07-12 |
COMC-3140 |
ComCam Installed on TMA |
2024-07-29 |
2024-07-23 |
COMC-3150 |
M1M3 Glass on TMA |
2024-09-16 |
2024-08-07 |
COMC-3160 |
ComCam First Photon |
2024-09-17 |
2024-08-08 |
COMC-3200 |
LSSTCam Reverification End |
2024-09-19 |
2024-09-19 |
COMC-3180 |
ComCam off Sky |
2024-11-11 |
2024-10-02 |
COMC-3190 |
ComCam off TMA |
2024-11-18 |
2024-10-09 |
COMC-3210 |
LSSTCam on Top End Assembly |
2024-12-02 |
2024-10-23 |
COMC-3220 |
LSSTCam L3 Checkout Done |
2024-12-16 |
2024-11-06 |
COMC-3230 |
LSSTCam on TMA |
2024-12-31 |
2024-11-21 |
COMC-3240 |
TMA Aligned |
2025-01-07 |
2024-11-28 |
COMC-3250 |
Rubin First Photon |
2025-02-24 |
2025-01-15 |
COMC-3260 |
TMA Pointing Models Complete |
2025-03-13 |
2025-02-03 |
COMC-3270 |
TMA AOS Ready |
2025-04-09 |
2025-02-28 |
COMC-3280 |
Rubin First Light |
2025-05-15 |
2025-04-07 |
COMC-3290 |
Rubin SV1 Start |
2025-07-09 |
2025-05-30 |
COMC-3300 |
Rubin SV2 Start |
2025-07-09 |
2025-05-30 |
COMC-3310 |
Rubin Eng Prep for OPS Start |
2025-08-05 |
2025-06-26 |
COMC-3320 |
Rubin Operations Readiness Review |
2025-08-12 |
2025-07-03 |
A public HTML version for embedding is here.
Download the PDF of this Block Schedule here.
Acronym |
Description |
---|---|
AI |
Artificial Intelligence |
AI&T |
Assembly Integration & Test |
AP |
Alert Production |
CCW |
Camera Cable Wrap |
COMP |
COMPlete |
ComCam |
The commissioning camera is a single-raft, 9-CCD camera that will be installed in LSST during commissioning, before the final camera is ready. |
DM |
Data Management |
EPO |
Education and Public Outreach |
HTML |
HyperText Markup Language |
LDM |
LSST Data Management (Document Handle) |
LSST |
Legacy Survey of Space and Time (formerly Large Synoptic Survey Telescope) |
M1M3 |
Primary Mirror Tertiary Mirror |
M2 |
Secondary Mirror |
OCS |
Observatory Control System |
Portable Document Format |
|
SC |
System Commissioning |
SITCOM |
System Integration, Test and Commissioning |
SLAC |
SLAC National Accelerator Laboratory |
SSP |
Solar System Processing |
SV |
Science Validation |
TCS |
Telescope Control System |
TMA |
Telescope Mount Assembly |