Celebratory Milestones#
Provenance#
This document was generated based on the contents of the lsst-dm/milestones repository, version 0b5c4af9, dated 2024-03-23. This corresponds to the status recorded in the project controls system for January 2024. This compares to December 2023.
Top milestones#
Code  | 
Name  | 
Due  | 
Previously  | 
|---|---|---|---|
EPOC285  | 
EPO Construction Finish  | 
2022-09-30  | 
Completed  | 
T&SC-0400-1730  | 
TMA Handoff to Rubin  | 
2023-03-31  | 
Completed  | 
CAMM8090  | 
COMP: Camera Pre-Ship Review at SLAC  | 
2024-04-25  | 
2024-03-26  | 
SUMMIT-Oct24-160  | 
ComCam Reinstalled on TMA  | 
2024-06-26  | 
2024-06-17  | 
T&SC-1100-0400  | 
3-Mirror Optical System Ready for Testing  | 
2024-07-05  | 
2024-07-22  | 
COMC-060200-20930  | 
Camera Ready for Full System AI&T  | 
2024-10-08  | 
2024-09-17  | 
T&SC-0400-0950  | 
Dome Complete  | 
2024-12-16  | 
2024-12-16  | 
SITCOM-122  | 
LSSTCam Ready for On Sky (First Photon)  | 
2025-01-14  | 
2025-02-19  | 
LSST-1520  | 
System First Light with LSSTCam  | 
2025-02-27  | 
2025-04-04  | 
LDM-503-17a  | 
Test report: Final Pipelines Delivery  | 
2025-06-25  | 
2025-07-31  | 
COMC-0654-0430  | 
COMP: Science Validation Surveys Complete  | 
2025-06-25  | 
2025-07-31  | 
SITCOM-130  | 
Operation Readiness Review Complete  | 
2025-07-02  | 
2025-08-07  | 
A public HTML version for embedding is here.
Supporting milestones#
Code  | 
Name  | 
Due  | 
Previously  | 
|---|---|---|---|
LDM-503-11a  | 
ComCam Ops Readiness  | 
2020-12-31  | 
Completed  | 
EPO-M6  | 
User Interfaces Complete  | 
2022-09-30  | 
Completed  | 
EPOC304  | 
Citizen Science Commissioning Project running via LSST infrastructure Complete  | 
2022-09-30  | 
Completed  | 
SITCOM-92  | 
Camera support asmy w/ComCam+PF+Int#1+CCW Installed on Telescope  | 
2022-12-01  | 
Completed  | 
LDM-503-13  | 
Ops rehearsal for data release processing #1  | 
2023-02-28  | 
Completed  | 
DM-27734  | 
Completion of the Scheduler  | 
2023-06-30  | 
Completed  | 
SITCOM-127  | 
M2 coating decision  | 
2023-10-01  | 
Completed  | 
LSST4820  | 
Love Contract Complete  | 
2023-11-01  | 
Completed  | 
DM-35987  | 
OCS Available on Summit  | 
2024-02-01  | 
2024-01-02  | 
DM-35989  | 
TCS Demonstrated  | 
2024-02-01  | 
2024-01-02  | 
SITCOM-102  | 
TMA safe for transition to M1M3 glass mirror  | 
2024-02-01  | 
2024-01-02  | 
SITCOM-97  | 
M1M3 cell+Surrogate Dynamic Testing on TMA done  | 
2024-02-01  | 
2024-02-05  | 
SITCOM-105  | 
ComCam + PF re-Installed on TMA  | 
2024-02-02  | 
2024-01-03  | 
SUMMIT-2976  | 
LSSTCam Received @ Summit  | 
2024-05-15  | 
2024-04-23  | 
SITCOM-104  | 
M2 Glass installed on Cell  | 
2024-05-15  | 
2024-05-23  | 
DM-35988  | 
M2 Software demonstrated  | 
2024-06-03  | 
2024-05-02  | 
SITCOM-109  | 
M1M3 Mirror Coating completed  | 
2024-06-07  | 
2024-06-24  | 
T&SC-1100-0300  | 
M2 Installed on Telescope  | 
2024-06-20  | 
2024-06-11  | 
SITCOM-110  | 
M1M3 installed on the TMA  | 
2024-07-05  | 
2024-07-22  | 
SITCOM-125  | 
LSSTCam reverification complete  | 
2024-10-08  | 
2024-09-17  | 
SITCOM-123  | 
LSSTCam Installed on TMA  | 
2024-11-20  | 
2025-01-29  | 
New1135  | 
LSSTCam Cold  | 
2025-01-07  | 
2025-02-12  | 
SUMMIT-3023  | 
COMP: TMA Refrigeration Tests Complete  | 
2025-01-29  | 
2025-01-29  | 
New1110  | 
Full focal plane readout complete  | 
2025-01-30  | 
2025-03-07  | 
New1165  | 
Telescope Aligned  | 
2025-01-31  | 
2025-03-10  | 
DM-AP-17  | 
Solar System Processing pipeline (SSP) available.  | 
2025-02-27  | 
2025-04-04  | 
SITCOM-116  | 
Initial Optical testing on TMA complete  | 
2025-02-27  | 
2025-04-04  | 
SITCOM-121  | 
System First Light with LSSTCam  | 
2025-02-27  | 
2025-04-04  | 
COMC-0140  | 
Start SV Data Collection  | 
2025-04-04  | 
2025-05-12  | 
DM-AP-16  | 
Full integration of the Alert Production system within the operational environment.  | 
2025-06-25  | 
2025-07-31  | 
LDM-503-16  | 
Ops rehearsal for data processing #3  | 
2025-07-02  | 
2025-08-07  | 
Download the PDF of this Block Schedule here.
Acronym  | 
Description  | 
|---|---|
AI  | 
Artificial Intelligence  | 
AI&T  | 
Assembly Integration & Test  | 
AP  | 
Alert Production  | 
CCW  | 
Camera Cable Wrap  | 
COMP  | 
COMPlete  | 
ComCam  | 
The commissioning camera is a single-raft, 9-CCD camera that will be installed in LSST during commissioning, before the final camera is ready.  | 
DM  | 
Data Management  | 
EPO  | 
Education and Public Outreach  | 
HTML  | 
HyperText Markup Language  | 
LDM  | 
LSST Data Management (Document Handle)  | 
LSST  | 
Legacy Survey of Space and Time (formerly Large Synoptic Survey Telescope)  | 
M1M3  | 
Primary Mirror Tertiary Mirror  | 
M2  | 
Secondary Mirror  | 
OCS  | 
Observatory Control System  | 
Portable Document Format  | 
|
SC  | 
System Commissioning  | 
SITCOM  | 
System Integration, Test and Commissioning  | 
SLAC  | 
SLAC National Accelerator Laboratory  | 
SSP  | 
Solar System Processing  | 
SV  | 
Science Validation  | 
TCS  | 
Telescope Control System  | 
TMA  | 
Telescope Mount Assembly  |