Due | Name | Previously |
---|---|---|
30-Sep-2022 | EPO Construction Finish | **Completed** |
31-Mar-2023 | TMA Handoff to Rubin | **Completed** |
25-Apr-2024 | COMP: Camera Pre-Ship Review at SLAC | 2024-03-26 |
26-Jun-2024 | ComCam Reinstalled on TMA | 2024-06-17 |
05-Jul-2024 | 3-Mirror Optical System Ready for Testing | 2024-07-22 |
08-Oct-2024 | Camera Ready for Full System AI&T | 2024-09-17 |
16-Dec-2024 | Dome Complete | 2024-12-16 |
14-Jan-2025 | LSSTCam Ready for On Sky (First Photon) | 2025-02-19 |
27-Feb-2025 | System First Light with LSSTCam | 2025-04-04 |
25-Jun-2025 | Test report: Final Pipelines Delivery | 2025-07-31 |
25-Jun-2025 | COMP: Science Validation Surveys Complete | 2025-07-31 |
02-Jul-2025 | Operation Readiness Review Complete | 2025-08-07 |
Using January 2024 project controls data. This compares to December 2023.