DMTN-232: Celebratory Milestones

  • William O'Mullane

Latest Revision: 2022-12-08

Provenance

This document was generated based on the contents of the lsst-dm/milestones repository, version fa9e8823, dated 2022-12-08. This corresponds to the status recorded in the project controls system for October 2022.

Top milestones

  • 2023-01-31 : TMA Handoff to Rubin (T&SC-0400-1730)
  • 2023-05-12 : COMP: Camera Pre-Ship Review at SLAC (CAMM8090)
  • 2023-09-29 : EPO Construction Finish (EPOC285)
  • 2023-12-05 : Camera Ready for Full System AI&T (COMC-060200-20930)
  • 2023-12-21 : Dome Complete (T&SC-0400-0950)
  • 2024-03-11 : 3-Mirror Optical System Ready for Testing (T&SC-1100-0400)
  • 2024-07-09 : System First Light (LSST-1520)
  • 2024-11-04 : Test report: Final Pipelines Delivery (LDM-503-17a)
  • 2024-11-04 : Mini-Survey 2 Complete (COMC-0654-0430)
  • 2024-11-11 : Operation Readiness Review Complete (SITCOM-130)

A public HTML version for embedding is here.

Supporting milestones

  • 2020-12-31 : ComCam Ops Readiness (LDM-503-11a)
  • 2022-09-30 : User Interfaces Complete (EPO-M6)
  • 2022-09-30 : Citizen Science Commissioning Project running via LSST infrastructure Complete (EPOC304)
  • 2022-10-03 : Completion of the Scheduler (DM-27734)
  • 2022-10-03 : Start SV Data Collection (COMC-0140)
  • 2022-10-03 : M2 coating decision (SITCOM-127)
  • 2022-10-03 : M2 Glass installed on Cell (SITCOM-104)
  • 2022-10-03 : Optical testing on TMA complete (SITCOM-116)
  • 2022-10-06 : COMP: Camera Ready for Verification Testing (ITC00475_COM)
  • 2022-11-17 : M2 Installed on Telescope (T&SC-1100-0300)
  • 2022-12-28 : Camera support asmy w/ComCam+PF+Int#1+CCW Installed on Telescope (SITCOM-92)
  • 2023-02-07 : M2 Software demonstrated (DM-35988)
  • 2023-03-30 : TMA safe for transition to M1M3 glass mirror (SITCOM-102)
  • 2023-05-05 : M1M3 cell+Surrogate Dynamic Testing on TMA done (SITCOM-97)
  • 2023-05-31 : OCS Available on Summit (DM-35987)
  • 2023-05-31 : TCS Demonstrated (DM-35989)
  • 2023-06-07 : LSSTCam Received @ Summit (SUMMIT-2976)
  • 2023-07-04 : COMP: TMA Refrigeration Tests Complete (SUMMIT-3023)
  • 2023-07-17 : ComCam + PF re-Installed on TMA (SITCOM-105)
  • 2023-11-01 : Love Contract Complete (LSST4820)
  • 2023-12-05 : Ops rehearsal for data release processing #1 (LDM-503-13)
  • 2023-12-05 : LSSTCam reverification complete (SITCOM-125)
  • 2024-02-09 : LSSTCam Installed on TMA (SITCOM-123)
  • 2024-03-11 : M1M3 installed on the TMA (SITCOM-110)
  • 2024-03-29 : LSSTCam Cold (New1135)
  • 2024-04-23 : Full focal plane readout complete (New1110)
  • 2024-05-07 : Telescope Aligned (New1165)
  • 2024-07-09 : Ops rehearsal for data release processing #3 (LDM-503-16)
  • 2024-07-09 : Solar System Processing pipeline available. (DM-AP-17)
  • 2024-11-04 : Full integration of the Alert Production system within the operational environment. (DM-AP-16)
Acronym Description
AI Artificial Intelligence
AI&T Assembly Integration & Test
AP Alert Production
CCW Camera Cable Wrap
COMP COMPlete
ComCam The commissioning camera is a single-raft, 9-CCD camera that will be installed in LSST during commissioning, before the final camera is ready.
DM Data Management
EPO Education and Public Outreach
LDM LSST Data Management (Document Handle)
LSST Legacy Survey of Space and Time (formerly Large Synoptic Survey Telescope)
M1M3 Primary Mirror Tertiary Mirror
M2 Secondary Mirror
SC Science Collaboration
SITCOM System Integration, Test and Commissioning
SLAC SLAC National Accelerator Laboratory
TMA Telescope Mount Assembly