| Due | Name |
|---|---|
| 30-Sep-2022 | EPO Construction Finish (Completed 30-Sep-2022) |
| 31-Jan-2023 | TMA Handoff to Rubin |
| 12-Jul-2023 | COMP: Camera Pre-Ship Review at SLAC |
| 21-Dec-2023 | Dome Complete |
| 05-Feb-2024 | Camera Ready for Full System AI&T |
| 25-Mar-2024 | 3-Mirror Optical System Ready for Testing |
| 06-Aug-2024 | System First Light |
| 02-Dec-2024 | Test report: Final Pipelines Delivery |
| 02-Dec-2024 | COMP: Science Validation Surveys Complete |
| 09-Dec-2024 | Operation Readiness Review Complete |
Using November 2022 project controls data.