Due | Name |
---|---|
30-Sep-2022 | EPO Construction Finish |
18-Oct-2022 | TMA Contract Complete |
28-Mar-2023 | Dome Complete |
01-May-2023 | COMP: Camera Pre-Ship Review at SLAC |
02-Jun-2023 | 3-Mirror Optical System Ready for Testing |
19-Jul-2023 | Engineering First Light w/ComCam |
17-Oct-2023 | Camera Ready for Full System AI&T |
13-Mar-2024 | System First Light |
09-Jul-2024 | Test report: Final Pipelines Delivery |
09-Jul-2024 | Mini-Survey 2 Complete |
16-Jul-2024 | Operation Readiness Review Complete |
Using July 2022 project controls data.