| Due | Name | Previously |
|---|---|---|
| 30-Sep-2022 | EPO Construction Finish | **Completed** |
| 31-Mar-2023 | TMA Handoff to Rubin | **Completed** |
| 07-May-2024 | COMP: Camera Pre-Ship Review at SLAC | 2024-04-25 |
| 12-Jul-2024 | 3-Mirror Optical System Ready for Testing | 2024-07-05 |
| 25-Jul-2024 | ComCam Reinstalled on TMA | 2024-06-26 |
| 15-Oct-2024 | Camera Ready for Full System AI&T | 2024-10-08 |
| 16-Dec-2024 | Dome Complete | 2024-12-16 |
| 21-Jan-2025 | LSSTCam Ready for On Sky (First Photon) | 2025-01-14 |
| 06-Mar-2025 | System First Light with LSSTCam | 2025-02-27 |
| 02-Jul-2025 | Test report: Final Pipelines Delivery | 2025-06-25 |
| 02-Jul-2025 | COMP: Science Validation Surveys Complete | 2025-06-25 |
| 09-Jul-2025 | Operation Readiness Review Complete | 2025-07-02 |
Using February 2024 project controls data. This compares to January 2024.