DueName Previously
30-Sep-2022 EPO Construction Finish**Completed**
31-Mar-2023 TMA Handoff to Rubin**Completed**
07-May-2024 COMP: Camera Pre-Ship Review at SLAC2024-04-25
12-Jul-2024 3-Mirror Optical System Ready for Testing2024-07-05
25-Jul-2024 ComCam Reinstalled on TMA2024-06-26
15-Oct-2024 Camera Ready for Full System AI&T2024-10-08
16-Dec-2024 Dome Complete2024-12-16
21-Jan-2025 LSSTCam Ready for On Sky (First Photon)2025-01-14
06-Mar-2025 System First Light with LSSTCam2025-02-27
02-Jul-2025 Test report: Final Pipelines Delivery2025-06-25
02-Jul-2025 COMP: Science Validation Surveys Complete2025-06-25
09-Jul-2025 Operation Readiness Review Complete2025-07-02

Using February 2024 project controls data. This compares to January 2024.