Due | Name |
---|---|
30-Sep-2022 | EPO Construction Finish (Completed 30-Sep-2022) |
31-Mar-2023 | TMA Handoff to Rubin (Completed 31-Mar-2023) |
02-Oct-2023 | COMP: Camera Pre-Ship Review at SLAC |
12-Apr-2024 | Camera Ready for Full System AI&T |
29-Apr-2024 | Dome Complete |
10-May-2024 | 3-Mirror Optical System Ready for Testing |
05-Jul-2024 | LSSTCam Ready for On Sky (First Photon) |
15-Oct-2024 | System First Light with LSSTCam |
10-Feb-2025 | Test report: Final Pipelines Delivery |
10-Feb-2025 | COMP: Science Validation Surveys Complete |
17-Feb-2025 | Operation Readiness Review Complete |
Using May 2023 project controls data.