DueName Previously
02-Feb-2024 M1M3 Lift Test**Completed**
08-Feb-2024 TMA Final Testing Begins**Completed**
16-Feb-2024 M1M3 Glass Lift Prep**Completed**
19-Feb-2024 Pathfinder Testing starts**Completed**
20-Mar-2024 M1M3 Glass Installed**Completed**
25-Apr-2024 TMA Final Testing Complete**Completed**
29-Apr-2024 M1M3 Coating Begins**Completed**
29-Apr-2024 LSSTCam Arrival Allowed**Completed**
10-May-2024 ComCam Removed from TMA2024-05-29
10-May-2024 LSSTCam Pack and Transport2024-05-29
15-May-2024 LSSTCam Received @ Summit2024-05-15
22-May-2024 M2 Cell Removed from TMA2024-05-07
12-Jun-2024 M2 Glass Installed2024-06-19
26-Jun-2024 M2 Glass on TMA2024-07-03
05-Jul-2024 ComCam Installed on TMA2024-07-12
19-Jul-2024 LSSTCam Reverification Start2024-07-19
31-Jul-2024 M1M3 Glass on TMA2024-07-26
01-Aug-2024 ComCam First Photon2024-07-29
25-Sep-2024 ComCam off Sky2024-09-20
25-Sep-2024 LSSTCam Reverification End2024-09-25
02-Oct-2024 ComCam off TMA2024-09-27
16-Oct-2024 LSSTCam on Top End Assembly2024-10-11
30-Oct-2024 LSSTCam L3 Checkout Done2024-10-25
14-Nov-2024 LSSTCam on TMA2024-11-11
21-Nov-2024 TMA Aligned2024-11-18
08-Jan-2025 Rubin First Photon2025-01-03
27-Jan-2025 TMA Pointing Models Complete2025-01-22
21-Feb-2025 TMA AOS Ready2025-02-18
31-Mar-2025 Rubin First Light2025-03-26
23-May-2025 Rubin SV1 Start2025-05-20
23-May-2025 Rubin SV2 Start2025-05-20
19-Jun-2025 Rubin Eng Prep for OPS Start2025-06-16
26-Jun-2025 Rubin Operations Readiness Review2025-06-23

Using April 2024 project controls data. This compares to March 2024.