Due | Name |
---|---|
30-Sep-2022 | EPO Construction Finish |
21-Oct-2022 | TMA Contract Complete |
13-Mar-2023 | COMP: Camera Pre-Ship Review at SLAC |
29-Mar-2023 | Dome Complete |
20-Jul-2023 | 3-Mirror Optical System Ready for Testing |
10-Aug-2023 | Engineering First Light w/ComCam |
11-Oct-2023 | Camera Ready for Full System AI&T |
14-Feb-2024 | System First Light |
11-Jun-2024 | Test report: Final Pipelines Delivery |
11-Jun-2024 | Mini-Survey 2 Complete |
18-Jun-2024 | Operation Readiness Review Complete |
Using May 2022 project controls data.