DMTN-232: Celebratory Milestones

  • William O'Mullane

Latest Revision: 2023-01-04

Provenance

This document was generated based on the contents of the lsst-dm/milestones repository, version 09119998, dated 2023-01-04. This corresponds to the status recorded in the project controls system for November 2022.

Top milestones

  • 2022-09-30 : EPO Construction Finish (EPOC285) Completed 2022-09-30
  • 2023-01-31 : TMA Handoff to Rubin (T&SC-0400-1730)
  • 2023-07-12 : COMP: Camera Pre-Ship Review at SLAC (CAMM8090)
  • 2023-12-21 : Dome Complete (T&SC-0400-0950)
  • 2024-02-05 : Camera Ready for Full System AI&T (COMC-060200-20930)
  • 2024-03-25 : 3-Mirror Optical System Ready for Testing (T&SC-1100-0400)
  • 2024-08-06 : System First Light (LSST-1520)
  • 2024-12-02 : Test report: Final Pipelines Delivery (LDM-503-17a)
  • 2024-12-02 : COMP: Science Validation Surveys Complete (COMC-0654-0430)
  • 2024-12-09 : Operation Readiness Review Complete (SITCOM-130)

A public HTML version for embedding is here.

Supporting milestones

  • 2020-12-31 : ComCam Ops Readiness (LDM-503-11a) Completed 2020-12-31
  • 2022-09-30 : User Interfaces Complete (EPO-M6) Completed 2022-09-30
  • 2022-09-30 : Citizen Science Commissioning Project running via LSST infrastructure Complete (EPOC304) Completed 2022-09-30
  • 2022-12-01 : Completion of the Scheduler (DM-27734)
  • 2022-12-01 : Start SV Data Collection (COMC-0140)
  • 2022-12-01 : M2 coating decision (SITCOM-127)
  • 2022-12-01 : M1M3 installed on the TMA (SITCOM-110)
  • 2023-01-17 : M2 Installed on Telescope (T&SC-1100-0300)
  • 2023-02-27 : Camera support asmy w/ComCam+PF+Int#1+CCW Installed on Telescope (SITCOM-92)
  • 2023-03-03 : COMP: Camera Ready for Verification Testing (ITC00475_COM)
  • 2023-03-30 : TMA safe for transition to M1M3 glass mirror (SITCOM-102)
  • 2023-04-06 : M2 Software demonstrated (DM-35988)
  • 2023-05-05 : M1M3 cell+Surrogate Dynamic Testing on TMA done (SITCOM-97)
  • 2023-05-31 : OCS Available on Summit (DM-35987)
  • 2023-05-31 : TCS Demonstrated (DM-35989)
  • 2023-06-23 : M2 Glass installed on Cell (SITCOM-104)
  • 2023-07-17 : ComCam + PF re-Installed on TMA (SITCOM-105)
  • 2023-08-04 : LSSTCam Received @ Summit (SUMMIT-2976)
  • 2023-08-25 : COMP: TMA Refrigeration Tests Complete (SUMMIT-3023)
  • 2024-01-03 : Love Contract Complete (LSST4820)
  • 2024-02-05 : Ops rehearsal for data release processing #1 (LDM-503-13)
  • 2024-02-05 : LSSTCam reverification complete (SITCOM-125)
  • 2024-03-04 : LSSTCam Installed on TMA (SITCOM-123)
  • 2024-04-19 : LSSTCam Cold (New1135)
  • 2024-05-14 : Full focal plane readout complete (New1110)
  • 2024-06-04 : Telescope Aligned (New1165)
  • 2024-08-06 : Ops rehearsal for data release processing #3 (LDM-503-16)
  • 2024-08-06 : Solar System Processing pipeline available. (DM-AP-17)
  • 2024-08-06 : Initial Optical testing on TMA complete (SITCOM-116)
  • 2024-12-02 : Full integration of the Alert Production system within the operational environment. (DM-AP-16)
Block Schedule

Download the PDF of this Block Schedule here.

Acronym Description
AI Artificial Intelligence
AI&T Assembly Integration & Test
AP Alert Production
CCW Camera Cable Wrap
COMP COMPlete
ComCam The commissioning camera is a single-raft, 9-CCD camera that will be installed in LSST during commissioning, before the final camera is ready.
DM Data Management
EPO Education and Public Outreach
LDM LSST Data Management (Document Handle)
LSST Legacy Survey of Space and Time (formerly Large Synoptic Survey Telescope)
M1M3 Primary Mirror Tertiary Mirror
M2 Secondary Mirror
SC Science Collaboration
SITCOM System Integration, Test and Commissioning
SLAC SLAC National Accelerator Laboratory
TMA Telescope Mount Assembly