DueName
03-Oct-2022 DELETE Engineering First Light w/ComCam
31-Jan-2023 TMA Contract Complete
31-Jan-2023 TMA Handoff to Rubin
12-May-2023 COMP: Camera Pre-Ship Review at SLAC
29-Sep-2023 EPO Construction Finish
05-Dec-2023 Camera Ready for Full System AI&T
21-Dec-2023 Dome Complete
11-Mar-2024 3-Mirror Optical System Ready for Testing
09-Jul-2024 System First Light
04-Nov-2024 Test report: Final Pipelines Delivery
04-Nov-2024 Mini-Survey 2 Complete
11-Nov-2024 Operation Readiness Review Complete

Using October 2022 project controls data.