Provenance¶
This document was generated based on the contents of the lsst-dm/milestones repository, version b6b03376, dated 2022-12-08. This corresponds to the status recorded in the project controls system for October 2022.
Top milestones¶
- 2022-10-03 : DELETE Engineering First Light w/ComCam (LSST-1513)
- 2023-01-31 : TMA Contract Complete (T&SC-1404-0750)
- 2023-01-31 : TMA Handoff to Rubin (T&SC-0400-1730)
- 2023-05-12 : COMP: Camera Pre-Ship Review at SLAC (CAMM8090)
- 2023-09-29 : EPO Construction Finish (EPOC285)
- 2023-12-05 : Camera Ready for Full System AI&T (COMC-060200-20930)
- 2023-12-21 : Dome Complete (T&SC-0400-0950)
- 2024-03-11 : 3-Mirror Optical System Ready for Testing (T&SC-1100-0400)
- 2024-07-09 : System First Light (LSST-1520)
- 2024-11-04 : Test report: Final Pipelines Delivery (LDM-503-17a)
- 2024-11-04 : Mini-Survey 2 Complete (COMC-0654-0430)
- 2024-11-11 : Operation Readiness Review Complete (SITCOM-130)
A public HTML version for embedding is here.
Supporting milestones¶
- 2020-12-31 : ComCam Ops Readiness (LDM-503-11a)
- 2022-09-30 : User Interfaces Complete (EPO-M6)
- 2022-09-30 : Citizen Science Commissioning Project running via LSST infrastructure Complete (EPOC304)
- 2022-10-03 : Completion of the Scheduler (DM-27734)
- 2022-10-03 : Start SV Data Collection (COMC-0140)
- 2022-10-03 : M2 coating decision (SITCOM-127)
- 2022-10-03 : M2 Glass installed on Cell (SITCOM-104)
- 2022-10-03 : Optical testing on TMA complete (SITCOM-116)
- 2022-10-06 : COMP: Camera Ready for Verification Testing (ITC00475_COM)
- 2022-11-17 : M2 Installed on Telescope (T&SC-1100-0300)
- 2022-12-28 : Camera support asmy w/ComCam+PF+Int#1+CCW Installed on Telescope (SITCOM-92)
- 2023-02-07 : M2 Software demonstrated (DM-35988)
- 2023-03-30 : TMA safe for transition to M1M3 glass mirror (SITCOM-102)
- 2023-05-05 : M1M3 cell+Surrogate Dynamic Testing on TMA done (SITCOM-97)
- 2023-05-31 : OCS Available on Summit (DM-35987)
- 2023-05-31 : TCS Demonstrated (DM-35989)
- 2023-06-07 : LSSTCam Received @ Summit (SUMMIT-2976)
- 2023-07-04 : COMP: TMA Refrigeration Tests Complete (SUMMIT-3023)
- 2023-07-17 : ComCam + PF re-Installed on TMA (SITCOM-105)
- 2023-11-01 : Love Contract Complete (LSST4820)
- 2023-12-05 : Ops rehearsal for data release processing #1 (LDM-503-13)
- 2023-12-05 : LSSTCam reverification complete (SITCOM-125)
- 2024-02-09 : LSSTCam Installed on TMA (SITCOM-123)
- 2024-03-11 : M1M3 installed on the TMA (SITCOM-110)
- 2024-03-29 : LSSTCam Cold (New1135)
- 2024-04-23 : Full focal plane readout complete (New1110)
- 2024-05-07 : Telescope Aligned (New1165)
- 2024-07-09 : Ops rehearsal for data release processing #3 (LDM-503-16)
- 2024-07-09 : Solar System Processing pipeline available. (DM-AP-17)
- 2024-11-04 : Full integration of the Alert Production system within the operational environment. (DM-AP-16)
Acronym | Description |
---|---|
AI | Artificial Intelligence |
AI&T | Assembly Integration & Test |
AP | Alert Production |
CCW | Camera Cable Wrap |
COMP | COMPlete |
ComCam | The commissioning camera is a single-raft, 9-CCD camera that will be installed in LSST during commissioning, before the final camera is ready. |
DM | Data Management |
EPO | Education and Public Outreach |
LDM | LSST Data Management (Document Handle) |
LSST | Legacy Survey of Space and Time (formerly Large Synoptic Survey Telescope) |
M1M3 | Primary Mirror Tertiary Mirror |
M2 | Secondary Mirror |
SC | Science Collaboration |
SITCOM | System Integration, Test and Commissioning |
SLAC | SLAC National Accelerator Laboratory |
TMA | Telescope Mount Assembly |