DMTN-232: Celebratory Milestones

  • William O'Mullane

Latest Revision: 2022-12-19

Provenance

This document was generated based on the contents of the lsst-dm/milestones repository, version 536534e5, dated 2022-12-19. This corresponds to the status recorded in the project controls system for October 2022.

Top milestones

  • 2023-01-31 : TMA Handoff to Rubin (T&SC-0400-1730)
  • 2023-05-12 : COMP: Camera Pre-Ship Review at SLAC (CAMM8090)
  • 2023-09-29 : EPO Construction Finish (EPOC285)
  • 2023-12-21 : Dome Complete (T&SC-0400-0950)
  • 2023-12-27 : Camera Ready for Full System AI&T (COMC-060200-20930)
  • 2024-03-11 : 3-Mirror Optical System Ready for Testing (T&SC-1100-0400)
  • 2024-07-09 : System First Light (LSST-1520)
  • 2024-11-04 : Test report: Final Pipelines Delivery (LDM-503-17a)
  • 2024-11-04 : COMP: Science Validation Surveys Complete (COMC-0654-0430)
  • 2024-11-11 : Operation Readiness Review Complete (SITCOM-130)

A public HTML version for embedding is here.

Supporting milestones

  • 2020-12-31 : ComCam Ops Readiness (LDM-503-11a) Completed 2020-12-31
  • 2022-09-30 : User Interfaces Complete (EPO-M6) Completed 2022-09-30
  • 2022-09-30 : Citizen Science Commissioning Project running via LSST infrastructure Complete (EPOC304) Completed 2022-09-30
  • 2022-11-01 : Completion of the Scheduler (DM-27734)
  • 2022-11-01 : Optical testing on TMA complete (SITCOM-116)
  • 2022-12-19 : M2 Installed on Telescope (T&SC-1100-0300)
  • 2022-12-20 : COMP: Camera Ready for Verification Testing (ITC00475_COM)
  • 2023-01-27 : Camera support asmy w/ComCam+PF+Int#1+CCW Installed on Telescope (SITCOM-92)
  • 2023-03-09 : M2 Software demonstrated (DM-35988)
  • 2023-03-30 : TMA safe for transition to M1M3 glass mirror (SITCOM-102)
  • 2023-05-05 : M1M3 cell+Surrogate Dynamic Testing on TMA done (SITCOM-97)
  • 2023-05-31 : OCS Available on Summit (DM-35987)
  • 2023-05-31 : TCS Demonstrated (DM-35989)
  • 2023-06-07 : Start SV Data Collection (COMC-0140)
  • 2023-06-07 : LSSTCam Received @ Summit (SUMMIT-2976)
  • 2023-06-23 : M2 coating decision (SITCOM-127)
  • 2023-06-23 : M2 Glass installed on Cell (SITCOM-104)
  • 2023-07-17 : ComCam + PF re-Installed on TMA (SITCOM-105)
  • 2023-07-31 : COMP: TMA Refrigeration Tests Complete (SUMMIT-3023)
  • 2023-12-04 : Love Contract Complete (LSST4820)
  • 2023-12-27 : Ops rehearsal for data release processing #1 (LDM-503-13)
  • 2023-12-27 : LSSTCam reverification complete (SITCOM-125)
  • 2024-02-09 : LSSTCam Installed on TMA (SITCOM-123)
  • 2024-03-11 : M1M3 installed on the TMA (SITCOM-110)
  • 2024-03-29 : LSSTCam Cold (New1135)
  • 2024-04-23 : Full focal plane readout complete (New1110)
  • 2024-05-07 : Telescope Aligned (New1165)
  • 2024-07-09 : Ops rehearsal for data release processing #3 (LDM-503-16)
  • 2024-07-09 : Solar System Processing pipeline available. (DM-AP-17)
  • 2024-11-04 : Full integration of the Alert Production system within the operational environment. (DM-AP-16)
Block Schedule

Download the PDF of this Block Schedule here.

Acronym Description
AI Artificial Intelligence
AI&T Assembly Integration & Test
AP Alert Production
CCW Camera Cable Wrap
COMP COMPlete
ComCam The commissioning camera is a single-raft, 9-CCD camera that will be installed in LSST during commissioning, before the final camera is ready.
DM Data Management
EPO Education and Public Outreach
LDM LSST Data Management (Document Handle)
LSST Legacy Survey of Space and Time (formerly Large Synoptic Survey Telescope)
M1M3 Primary Mirror Tertiary Mirror
M2 Secondary Mirror
SC Science Collaboration
SITCOM System Integration, Test and Commissioning
SLAC SLAC National Accelerator Laboratory
TMA Telescope Mount Assembly