Due | Name |
---|---|
30-Sep-2022 | EPO Construction Finish (Completed 30-Sep-2022) |
17-Mar-2023 | TMA Handoff to Rubin |
02-Aug-2023 | COMP: Camera Pre-Ship Review at SLAC |
26-Feb-2024 | Camera Ready for Full System AI&T |
15-Apr-2024 | 3-Mirror Optical System Ready for Testing |
18-Apr-2024 | Dome Complete |
27-Aug-2024 | System First Light |
23-Dec-2024 | Test report: Final Pipelines Delivery |
23-Dec-2024 | COMP: Science Validation Surveys Complete |
30-Dec-2024 | Operation Readiness Review Complete |
Using February 2023 project controls data.