DueName
30-Sep-2022 EPO Construction Finish (Completed 30-Sep-2022)
28-Feb-2023 TMA Handoff to Rubin
21-Jun-2023 COMP: Camera Pre-Ship Review at SLAC
16-Jan-2024 Camera Ready for Full System AI&T
05-Apr-2024 3-Mirror Optical System Ready for Testing
18-Apr-2024 Dome Complete
12-Aug-2024 System First Light
06-Dec-2024 Test report: Final Pipelines Delivery
06-Dec-2024 COMP: Science Validation Surveys Complete
13-Dec-2024 Operation Readiness Review Complete

Using December 2022 project controls data.