DueName Previously
02-Feb-2024 M1M3 Lift Test**Completed**
08-Feb-2024 TMA Final Testing Begins**Completed**
16-Feb-2024 M1M3 Glass Lift Prep**Completed**
19-Feb-2024 Pathfinder Testing starts**Completed**
20-Mar-2024 M1M3 Glass Installed**Completed**
25-Apr-2024 TMA Final Testing Complete**Completed**
29-Apr-2024 M1M3 Coating Begins**Completed**
29-Apr-2024 LSSTCam Arrival Allowed**Completed**
10-May-2024 LSSTCam Pack and Transport**Completed**
16-May-2024 LSSTCam Received @ Summit**Completed**
24-May-2024 ComCam Removed from TMA**Completed**
03-Jul-2024 M2 Cell Removed from TMA07-Jun-2024
08-Jul-2024 M2 Glass Installed28-Jun-2024
15-Jul-2024 LSSTCam Reverification Start15-Jul-2024
18-Jul-2024 M2 Glass on TMA12-Jul-2024
29-Jul-2024 ComCam Installed on TMA23-Jul-2024
16-Sep-2024 M1M3 Glass on TMA07-Aug-2024
17-Sep-2024 ComCam First Photon08-Aug-2024
19-Sep-2024 LSSTCam Reverification End19-Sep-2024
11-Nov-2024 ComCam off Sky02-Oct-2024
18-Nov-2024 ComCam off TMA09-Oct-2024
02-Dec-2024 LSSTCam on Top End Assembly23-Oct-2024
16-Dec-2024 LSSTCam L3 Checkout Done06-Nov-2024
31-Dec-2024 LSSTCam on TMA21-Nov-2024
07-Jan-2025 TMA Aligned28-Nov-2024
24-Feb-2025 Rubin First Photon15-Jan-2025
13-Mar-2025 TMA Pointing Models Complete03-Feb-2025
09-Apr-2025 TMA AOS Ready28-Feb-2025
15-May-2025 Rubin First Light07-Apr-2025
09-Jul-2025 Rubin SV1 Start30-May-2025
09-Jul-2025 Rubin SV2 Start30-May-2025
05-Aug-2025 Rubin Eng Prep for OPS Start26-Jun-2025
12-Aug-2025 Rubin Operations Readiness Review03-Jul-2025

Using June 2024 project controls data. This compares to May 2024.