DMTN-232
Celebratory Milestones#
Provenance#
This document was generated based on the contents of the lsst-dm/milestones repository, version ee1aef22, dated 2025-08-20. This corresponds to the status recorded in the project controls system for May 2025. This compares to April 2025.
Key milestones#
Code  | 
Name  | 
Due  | 
Previously  | 
|---|---|---|---|
COMC-3010  | 
M1M3 Lift Test  | 
2024-02-02  | 
Completed  | 
COMC-3000  | 
TMA Final Testing Begins  | 
2024-02-08  | 
Completed  | 
COMC-3030  | 
M1M3 Glass Lift Prep  | 
2024-02-16  | 
Completed  | 
COMC-3020  | 
Pathfinder Testing starts  | 
2024-02-19  | 
Completed  | 
COMC-3040  | 
M1M3 Glass Installed  | 
2024-03-20  | 
Completed  | 
COMC-3050  | 
TMA Final Testing Complete  | 
2024-04-25  | 
Completed  | 
COMC-3060  | 
M1M3 Coating Begins  | 
2024-04-29  | 
Completed  | 
COMC-3090  | 
LSSTCam Arrival Allowed  | 
2024-04-29  | 
Completed  | 
COMC-3080  | 
LSSTCam Pack and Transport  | 
2024-05-10  | 
Completed  | 
SUMMIT-2976  | 
LSSTCam Received @ Summit  | 
2024-05-16  | 
Completed  | 
COMC-3070  | 
ComCam Removed from TMA  | 
2024-05-24  | 
Completed  | 
COMC-3110  | 
M2 Cell Removed from TMA  | 
2024-06-20  | 
Completed  | 
COMC-3120  | 
M2 Glass Installed  | 
2024-07-10  | 
Completed  | 
COMC-3130  | 
M2 Glass on TMA  | 
2024-07-25  | 
Completed  | 
COMC-3170  | 
LSSTCam Reverification Start  | 
2024-08-15  | 
Completed  | 
COMC-3140  | 
ComCam Installed on TMA  | 
2024-08-19  | 
Completed  | 
COMC-3160  | 
ComCam First Photon  | 
2024-10-04  | 
Completed  | 
COMC-3150  | 
M1M3 Glass on TMA  | 
2024-10-04  | 
Completed  | 
COMC-3220  | 
LSSTCam L3 Checkout Done  | 
2024-12-02  | 
Completed  | 
COMC-3200  | 
LSSTCam Reverification End  | 
2024-12-06  | 
Completed  | 
COMC-3180  | 
ComCam off Sky  | 
2024-12-12  | 
Completed  | 
COMC-3190  | 
ComCam off TMA  | 
2024-12-20  | 
Completed  | 
COMC-3210  | 
LSSTCam on Top End Assembly  | 
2025-02-05  | 
Completed  | 
COMC-3230  | 
LSSTCam on TMA  | 
2025-03-06  | 
Completed  | 
COMC-3240  | 
TMA Aligned  | 
2025-04-14  | 
Completed  | 
COMC-3250  | 
Rubin First Photon  | 
2025-04-15  | 
Completed  | 
COMC-3260  | 
TMA Pointing Models Complete  | 
2025-04-30  | 
Completed  | 
COMC-3270  | 
TMA AOS Ready  | 
2025-06-06  | 
2025-05-28  | 
COMC-3280  | 
Rubin First Light  | 
2025-07-04  | 
2025-07-03  | 
COMC-3290  | 
Rubin SV1 Start  | 
2025-07-04  | 
2025-07-03  | 
COMC-3300  | 
Rubin SV2 Start  | 
2025-07-18  | 
2025-07-17  | 
COMC-3310  | 
Rubin Eng Prep for OPS Start  | 
2025-09-11  | 
2025-09-10  | 
COMC-3320  | 
Rubin Operations Readiness Review  | 
2025-09-18  | 
2025-09-17  | 
A public HTML version for embedding is here.
Download the PDF of this Block Schedule here.
Acronym  | 
Description  | 
|---|---|
AI  | 
Artificial Intelligence  | 
AI&T  | 
Assembly Integration & Test  | 
AP  | 
Alert Production  | 
CCW  | 
Camera Cable Wrap  | 
COMP  | 
COMPlete  | 
ComCam  | 
The commissioning camera is a single-raft, 9-CCD camera that will be installed in LSST during commissioning, before the final camera is ready.  | 
DM  | 
Data Management  | 
EPO  | 
Education and Public Outreach  | 
HTML  | 
HyperText Markup Language  | 
LDM  | 
LSST Data Management (Document Handle)  | 
LSST  | 
Legacy Survey of Space and Time (formerly Large Synoptic Survey Telescope)  | 
M1M3  | 
Primary Mirror Tertiary Mirror  | 
M2  | 
Secondary Mirror  | 
OCS  | 
Observatory Control System  | 
Portable Document Format  | 
|
SC  | 
System Commissioning  | 
SITCOM  | 
System Integration, Test and Commissioning  | 
SLAC  | 
SLAC National Accelerator Laboratory  | 
SSP  | 
Solar System Processing  | 
SV  | 
Science Validation  | 
TCS  | 
Telescope Control System  | 
TMA  | 
Telescope Mount Assembly  |