DMTN-232: Celebratory Milestones

  • William O'Mullane

Latest Revision: 2022-06-17

Provenance

This document was generated based on the contents of the lsst-dm/milestones repository, version 70b050bb, dated 2022-07-05. This corresponds to the status recorded in the project controls system for May 2022.

Top milestones

  • 2022-09-30 : EPO Construction Finish (EPOC285)
  • 2022-10-21 : TMA Contract Complete (T&SC-1404-0750)
  • 2023-03-13 : COMP: Camera Pre-Ship Review at SLAC (CAMM8090)
  • 2023-03-29 : Dome Complete (T&SC-0400-0950)
  • 2023-07-20 : 3-Mirror Optical System Ready for Testing (T&SC-1100-0400)
  • 2023-08-10 : Engineering First Light w/ComCam (LSST-1513)
  • 2023-10-11 : Camera Ready for Full System AI&T (COMC-060200-20930)
  • 2024-02-14 : System First Light (LSST-1520)
  • 2024-06-11 : Test report: Final Pipelines Delivery (LDM-503-17a)
  • 2024-06-11 : Mini-Survey 2 Complete (COMC-0654-0430)
  • 2024-06-18 : Operation Readiness Review Complete (SITCOM-130)

A public HTML version for embedding is here.

Supporting milestones

  • 2022-08-29 : COMP: Camera Ready for Verification Testing (ITC00475_COM)
  • 2022-09-22 : Camera support asmy w/ComCam+PF+Int#1+CCW Installed on Telescope (SITCOM-92)
  • 2022-09-30 : User Interfaces Complete (EPO-M6)
  • 2022-09-30 : Citizen Science Commissioning Project running via LSST infrastructure Complete (EPOC304)
  • 2022-12-23 : M1M3 cell+Surrogate Dynamic Testing on TMA done (SITCOM-97)
  • 2023-02-07 : M2 Glass installed on Cell (SITCOM-104)
  • 2023-03-01 : M2 Installed on Telescope (T&SC-1100-0300)
  • 2023-03-14 : ComCam + PF re-Installed on TMA (SITCOM-105)
  • 2023-03-21 : TMA safe for transition to M1M3 glass mirror (SITCOM-102)
  • 2023-04-05 : LSSTCam Received @ Summit (SUMMIT-2976)
  • 2023-05-15 : COMP: TMA Refrigeration Tests Complete (SUMMIT-3023)
  • 2023-07-20 : M1M3 installed on the TMA (SITCOM-110)
  • 2023-07-21 : Ops rehearsal for data release processing #1 (ComCam data) (LDM-503-13)
  • 2023-10-06 : Optical testing on TMA complete (SITCOM-116)
  • 2023-10-11 : LSSTCam reverification complete (SITCOM-125)
  • 2023-11-07 : M2 coating decision (SITCOM-127)
  • 2024-01-03 : LSSTCam Installed on TMA (SITCOM-123)
  • 2024-02-14 : Ops rehearsal for data release processing #3 (LDM-503-16)
  • 2024-02-14 : Solar System Processing pipeline available. (DM-AP-17)
  • 2024-03-21 : Begin Science Verification (COMC-0140)
  • 2024-06-11 : Full integration of the Alert Production system within the operational environment. (DM-AP-16)
Acronym Description
AI Artificial Intelligence
AI&T Assembly Integration & Test
AP Alert Production
CCW Camera Cable Wrap
COMP COMPlete
ComCam The commissioning camera is a single-raft, 9-CCD camera that will be installed in LSST during commissioning, before the final camera is ready.
DM Data Management
EPO Education and Public Outreach
LDM LSST Data Management (Document Handle)
LSST Legacy Survey of Space and Time (formerly Large Synoptic Survey Telescope)
M1M3 Primary Mirror Tertiary Mirror
M2 Secondary Mirror
SC Science Collaboration
SITCOM System Integration, Test and Commissioning
SLAC SLAC National Accelerator Laboratory
TMA Telescope Mount Assembly