DMTN-232: Celebratory Milestones

  • William O'Mullane

Latest Revision: 2022-06-09

Provenance

This document was generated based on the contents of the lsst-dm/milestones repository, version c8d5a73c, dated 2022-06-17. This corresponds to the status recorded in the project controls system for May 2022.

Top milestones

  • T&SC-1404-0750 : TMA Contract Complete [Due 2022-10-14]
  • CAMM8090 : COMP: Camera Pre-Ship Review at SLAC [Due 2023-02-27]
  • T&SC-0400-0950 : Dome Complete [Due 2023-03-29]
  • T&SC-1100-0400 : 3-Mirror Optical System Ready for Testing [Due 2023-07-13]
  • EPOC285 : EPO Construction Finish [Due 2023-08-31]
  • LSST-1513 : Engineering First Light w/ComCam [Due 2023-09-07]
  • COMC-060200-20930 : Camera Ready for Full System AI&T [Due 2023-10-03]
  • LSST-1520 : System First Light [Due 2024-01-18]
  • LDM-503-17a : Test report: Final Pipelines Delivery [Due 2024-06-05]
  • COMC-0654-0430 : Mini-Survey 2 Complete [Due 2024-06-05]
  • SITCOM-130 : Operation Readiness Review Complete [Due 2024-06-12]

Supporting milestones

  • ITC00475_COM : COMP: Camera Ready for Verification Testing [Due 2022-08-11]
  • SITCOM-92 : Camera support asmy w/ComCam+PF+Int#1+CCW Installed on Telescope [Due 2022-09-26]
  • EPOC304 : Citizen Science Commissioning Project running via LSST infrastructure Complete [Due 2022-11-29]
  • SITCOM-97 : M1M3 cell+Surrogate Dynamic Testing on TMA done [Due 2022-12-16]
  • SITCOM-104 : M2 Glass installed on Cell [Due 2023-01-31]
  • T&SC-1100-0300 : M2 Installed on Telescope [Due 2023-02-22]
  • SITCOM-105 : ComCam + PF re-Installed on TMA [Due 2023-03-07]
  • SITCOM-102 : TMA safe for transition to M1M3 glass mirror [Due 2023-03-14]
  • SUMMIT-2976 : LSSTCam Received @ Summit [Due 2023-03-22]
  • SUMMIT-3023 : COMP: TMA Refrigeration Tests Complete [Due 2023-05-02]
  • EPO-M6 : User Interfaces Complete [Due 2023-05-31]
  • SITCOM-110 : M1M3 installed on the TMA [Due 2023-07-13]
  • LDM-503-13 : Ops rehearsal for data release processing #1 (ComCam data) [Due 2023-07-14]
  • SITCOM-116 : Optical testing on TMA complete [Due 2023-09-29]
  • SITCOM-125 : LSSTCam reverification complete [Due 2023-10-03]
  • SITCOM-127 : M2 coating decision [Due 2023-10-30]
  • SITCOM-123 : LSSTCam Installed on TMA [Due 2023-12-26]
  • LDM-503-16 : Ops rehearsal for data release processing #3 [Due 2024-01-18]
  • DM-AP-17 : Solar System Processing pipeline available. [Due 2024-01-18]
  • COMC-0140 : Begin Science Verification [Due 2024-03-15]
  • DM-AP-16 : Full integration of the Alert Production system within the operational environment. [Due 2024-06-05]
Acronym Description
AI Artificial Intelligence
AI&T Assembly Integration & Test
AP Alert Production
CCW Camera Cable Wrap
COMP COMPlete
ComCam The commissioning camera is a single-raft, 9-CCD camera that will be installed in LSST during commissioning, before the final camera is ready.
DM Data Management
EPO Education and Public Outreach
LDM LSST Data Management (Document Handle)
LSST Legacy Survey of Space and Time (formerly Large Synoptic Survey Telescope)
M1M3 Primary Mirror Tertiary Mirror
M2 Secondary Mirror
SC Science Collaboration
SITCOM System Integration, Test and Commissioning
SLAC SLAC National Accelerator Laboratory
TMA Telescope Mount Assembly