| Due | Name | 
|---|---|
| 30-Sep-2022 | EPO Construction Finish | 
| 21-Oct-2022 | TMA Contract Complete | 
| 13-Mar-2023 | COMP: Camera Pre-Ship Review at SLAC | 
| 29-Mar-2023 | Dome Complete | 
| 20-Jul-2023 | 3-Mirror Optical System Ready for Testing | 
| 10-Aug-2023 | Engineering First Light w/ComCam | 
| 11-Oct-2023 | Camera Ready for Full System AI&T | 
| 14-Feb-2024 | System First Light | 
| 11-Jun-2024 | Test report: Final Pipelines Delivery | 
| 11-Jun-2024 | Mini-Survey 2 Complete | 
| 18-Jun-2024 | Operation Readiness Review Complete | 
Using May 2022 project controls data.