DueName
30-Sep-2022 EPO Construction Finish (Completed 30-Sep-2022)
31-Mar-2023 TMA Handoff to Rubin (Completed 31-Mar-2023)
20-Oct-2023 COMP: Camera Pre-Ship Review at SLAC
29-Apr-2024 Dome Complete
30-Apr-2024 Camera Ready for Full System AI&T
13-Jun-2024 3-Mirror Optical System Ready for Testing
24-Jul-2024 LSSTCam Ready for On Sky (First Photon)
01-Nov-2024 System First Light with LSSTCam
27-Feb-2025 Test report: Final Pipelines Delivery
27-Feb-2025 COMP: Science Validation Surveys Complete
06-Mar-2025 Operation Readiness Review Complete

Using June 2023 project controls data.