DMTN-232: Celebratory Milestones

  • William O'Mullane

Latest Revision: 2023-07-25

Provenance

This document was generated based on the contents of the lsst-dm/milestones repository, version ab9c5381, dated 2023-07-25. This corresponds to the status recorded in the project controls system for June 2023.

Top milestones

  • 2022-09-30 : EPO Construction Finish (EPOC285) Completed 2022-09-30
  • 2023-03-31 : TMA Handoff to Rubin (T&SC-0400-1730) Completed 2023-03-31
  • 2023-10-20 : COMP: Camera Pre-Ship Review at SLAC (CAMM8090)
  • 2024-04-29 : Dome Complete (T&SC-0400-0950)
  • 2024-04-30 : Camera Ready for Full System AI&T (COMC-060200-20930)
  • 2024-06-13 : 3-Mirror Optical System Ready for Testing (T&SC-1100-0400)
  • 2024-07-24 : LSSTCam Ready for On Sky (First Photon) (SITCOM-122)
  • 2024-11-01 : System First Light with LSSTCam (LSST-1520)
  • 2025-02-27 : Test report: Final Pipelines Delivery (LDM-503-17a)
  • 2025-02-27 : COMP: Science Validation Surveys Complete (COMC-0654-0430)
  • 2025-03-06 : Operation Readiness Review Complete (SITCOM-130)

A public HTML version for embedding is here.

Supporting milestones

  • 2020-12-31 : ComCam Ops Readiness (LDM-503-11a) Completed 2020-12-31
  • 2022-09-30 : User Interfaces Complete (EPO-M6) Completed 2022-09-30
  • 2022-09-30 : Citizen Science Commissioning Project running via LSST infrastructure Complete (EPOC304) Completed 2022-09-30
  • 2022-12-01 : Camera support asmy w/ComCam+PF+Int#1+CCW Installed on Telescope (SITCOM-92) Completed 2022-12-01
  • 2023-02-28 : Ops rehearsal for data release processing #1 (LDM-503-13) Completed 2023-02-28
  • 2023-06-30 : Completion of the Scheduler (DM-27734) Completed 2023-06-30
  • 2023-07-03 : OCS Available on Summit (DM-35987)
  • 2023-07-03 : TCS Demonstrated (DM-35989)
  • 2023-07-03 : TMA safe for transition to M1M3 glass mirror (SITCOM-102)
  • 2023-07-31 : M1M3 cell+Surrogate Dynamic Testing on TMA done (SITCOM-97)
  • 2023-10-03 : ComCam + PF re-Installed on TMA (SITCOM-105)
  • 2023-10-12 : COMP: TMA Refrigeration Tests Complete (SUMMIT-3023)
  • 2023-11-06 : LSSTCam Received @ Summit (SUMMIT-2976)
  • 2023-12-01 : Love Contract Complete (LSST4820)
  • 2024-02-29 : M2 Software demonstrated (DM-35988)
  • 2024-04-18 : M2 coating decision (SITCOM-127)
  • 2024-04-18 : M2 Glass installed on Cell (SITCOM-104)
  • 2024-04-30 : LSSTCam reverification complete (SITCOM-125)
  • 2024-05-03 : M2 Installed on Telescope (T&SC-1100-0300)
  • 2024-05-29 : LSSTCam Installed on TMA (SITCOM-123)
  • 2024-06-13 : M1M3 installed on the TMA (SITCOM-110)
  • 2024-07-17 : LSSTCam Cold (New1135)
  • 2024-08-09 : Full focal plane readout complete (New1110)
  • 2024-08-30 : Telescope Aligned (New1165)
  • 2024-11-01 : Solar System Processing pipeline available. (DM-AP-17)
  • 2024-11-01 : Initial Optical testing on TMA complete (SITCOM-116)
  • 2024-12-09 : Start SV Data Collection (COMC-0140)
  • 2025-02-27 : Full integration of the Alert Production system within the operational environment. (DM-AP-16)
  • 2025-03-06 : Ops rehearsal for data release processing #3 (LDM-503-16)
Block Schedule

Download the PDF of this Block Schedule here.

Acronym Description
AI Artificial Intelligence
AI&T Assembly Integration & Test
AP Alert Production
CCW Camera Cable Wrap
COMP COMPlete
ComCam The commissioning camera is a single-raft, 9-CCD camera that will be installed in LSST during commissioning, before the final camera is ready.
DM Data Management
EPO Education and Public Outreach
LDM LSST Data Management (Document Handle)
LSST Legacy Survey of Space and Time (formerly Large Synoptic Survey Telescope)
M1M3 Primary Mirror Tertiary Mirror
M2 Secondary Mirror
SC Science Collaboration
SITCOM System Integration, Test and Commissioning
SLAC SLAC National Accelerator Laboratory
TMA Telescope Mount Assembly