DueName Previously
02-Feb-2024 M1M3 Lift Test**Completed**
08-Feb-2024 TMA Final Testing Begins**Completed**
16-Feb-2024 M1M3 Glass Lift Prep**Completed**
19-Feb-2024 Pathfinder Testing starts**Completed**
20-Mar-2024 M1M3 Glass Installed**Completed**
25-Apr-2024 TMA Final Testing Complete**Completed**
29-Apr-2024 M1M3 Coating Begins**Completed**
29-Apr-2024 LSSTCam Arrival Allowed**Completed**
10-May-2024 LSSTCam Pack and Transport**Completed**
16-May-2024 LSSTCam Received @ Summit**Completed**
24-May-2024 ComCam Removed from TMA**Completed**
20-Jun-2024 M2 Cell Removed from TMA**Completed**
10-Jul-2024 M2 Glass Installed**Completed**
25-Jul-2024 M2 Glass on TMA**Completed**
15-Aug-2024 LSSTCam Reverification Start**Completed**
19-Aug-2024 ComCam Installed on TMA**Completed**
04-Oct-2024 M1M3 Glass on TMA12-Nov-2024
01-Nov-2024 ComCam First Photon12-Nov-2024
13-Nov-2024 LSSTCam Reverification End19-Nov-2024
16-Dec-2024 ComCam off Sky16-Dec-2024
23-Dec-2024 ComCam off TMA23-Dec-2024
06-Jan-2025 LSSTCam on Top End Assembly06-Jan-2025
20-Jan-2025 LSSTCam L3 Checkout Done20-Jan-2025
19-Feb-2025 LSSTCam on TMA04-Feb-2025
26-Feb-2025 TMA Aligned11-Feb-2025
15-Apr-2025 Rubin First Photon31-Mar-2025
01-May-2025 TMA Pointing Models Complete16-Apr-2025
29-May-2025 TMA AOS Ready14-May-2025
04-Jul-2025 Rubin First Light19-Jun-2025
15-Aug-2025 Rubin SV1 Start13-Aug-2025
15-Aug-2025 Rubin SV2 Start13-Aug-2025
11-Sep-2025 Rubin Eng Prep for OPS Start09-Sep-2025
18-Sep-2025 Rubin Operations Readiness Review16-Sep-2025

Using September 2024 project controls data. This compares to August 2024.