| Due | Name | 
|---|---|
| 30-Sep-2022 | EPO Construction Finish (Completed 30-Sep-2022) | 
| 03-Apr-2023 | TMA Handoff to Rubin | 
| 05-Sep-2023 | COMP: Camera Pre-Ship Review at SLAC | 
| 20-Mar-2024 | Dome Complete | 
| 04-Apr-2024 | Camera Ready for Full System AI&T | 
| 20-May-2024 | 3-Mirror Optical System Ready for Testing | 
| 28-Jun-2024 | LSSTCam Ready for On Sky (First Photon) | 
| 08-Oct-2024 | System First Light with LSSTCam | 
| 03-Feb-2025 | Test report: Final Pipelines Delivery | 
| 03-Feb-2025 | COMP: Science Validation Surveys Complete | 
| 10-Feb-2025 | Operation Readiness Review Complete | 
Using March 2023 project controls data.