DueName Previously
02-Feb-2024 M1M3 Lift Test**Completed**
08-Feb-2024 TMA Final Testing Begins**Completed**
16-Feb-2024 M1M3 Glass Lift Prep**Completed**
19-Feb-2024 Pathfinder Testing starts**Completed**
20-Mar-2024 M1M3 Glass Installed**Completed**
25-Apr-2024 TMA Final Testing Complete**Completed**
29-Apr-2024 M1M3 Coating Begins**Completed**
29-Apr-2024 LSSTCam Arrival Allowed**Completed**
10-May-2024 LSSTCam Pack and Transport**Completed**
16-May-2024 LSSTCam Received @ Summit**Completed**
24-May-2024 ComCam Removed from TMA**Completed**
20-Jun-2024 M2 Cell Removed from TMA**Completed**
10-Jul-2024 M2 Glass Installed**Completed**
25-Jul-2024 M2 Glass on TMA**Completed**
15-Aug-2024 LSSTCam Reverification Start**Completed**
19-Aug-2024 ComCam Installed on TMA**Completed**
04-Oct-2024 ComCam First Photon**Completed**
04-Oct-2024 M1M3 Glass on TMA**Completed**
02-Dec-2024 LSSTCam L3 Checkout Done**Completed**
06-Dec-2024 LSSTCam Reverification End**Completed**
12-Dec-2024 ComCam off Sky**Completed**
20-Dec-2024 ComCam off TMA**Completed**
28-Jan-2025 LSSTCam on Top End Assembly02-Jan-2025
28-Feb-2025 LSSTCam on TMA19-Feb-2025
07-Mar-2025 TMA Aligned26-Feb-2025
24-Apr-2025 Rubin First Photon15-Apr-2025
01-May-2025 TMA Pointing Models Complete01-May-2025
29-May-2025 TMA AOS Ready29-May-2025
04-Jul-2025 Rubin First Light04-Jul-2025
15-Aug-2025 Rubin SV1 Start15-Aug-2025
15-Aug-2025 Rubin SV2 Start15-Aug-2025
11-Sep-2025 Rubin Eng Prep for OPS Start11-Sep-2025
18-Sep-2025 Rubin Operations Readiness Review18-Sep-2025

Using December 2024 project controls data. This compares to November 2024.