Provenance¶
This document was generated based on the contents of the lsst-dm/milestones repository, version c8d5a73c, dated 2022-06-17. This corresponds to the status recorded in the project controls system for May 2022.
Top milestones¶
- T&SC-1404-0750 : TMA Contract Complete [Due 2022-10-14]
- CAMM8090 : COMP: Camera Pre-Ship Review at SLAC [Due 2023-02-27]
- T&SC-0400-0950 : Dome Complete [Due 2023-03-29]
- T&SC-1100-0400 : 3-Mirror Optical System Ready for Testing [Due 2023-07-13]
- EPOC285 : EPO Construction Finish [Due 2023-08-31]
- LSST-1513 : Engineering First Light w/ComCam [Due 2023-09-07]
- COMC-060200-20930 : Camera Ready for Full System AI&T [Due 2023-10-03]
- LSST-1520 : System First Light [Due 2024-01-18]
- LDM-503-17a : Test report: Final Pipelines Delivery [Due 2024-06-05]
- COMC-0654-0430 : Mini-Survey 2 Complete [Due 2024-06-05]
- SITCOM-130 : Operation Readiness Review Complete [Due 2024-06-12]
Supporting milestones¶
- ITC00475_COM : COMP: Camera Ready for Verification Testing [Due 2022-08-11]
- SITCOM-92 : Camera support asmy w/ComCam+PF+Int#1+CCW Installed on Telescope [Due 2022-09-26]
- EPOC304 : Citizen Science Commissioning Project running via LSST infrastructure Complete [Due 2022-11-29]
- SITCOM-97 : M1M3 cell+Surrogate Dynamic Testing on TMA done [Due 2022-12-16]
- SITCOM-104 : M2 Glass installed on Cell [Due 2023-01-31]
- T&SC-1100-0300 : M2 Installed on Telescope [Due 2023-02-22]
- SITCOM-105 : ComCam + PF re-Installed on TMA [Due 2023-03-07]
- SITCOM-102 : TMA safe for transition to M1M3 glass mirror [Due 2023-03-14]
- SUMMIT-2976 : LSSTCam Received @ Summit [Due 2023-03-22]
- SUMMIT-3023 : COMP: TMA Refrigeration Tests Complete [Due 2023-05-02]
- EPO-M6 : User Interfaces Complete [Due 2023-05-31]
- SITCOM-110 : M1M3 installed on the TMA [Due 2023-07-13]
- LDM-503-13 : Ops rehearsal for data release processing #1 (ComCam data) [Due 2023-07-14]
- SITCOM-116 : Optical testing on TMA complete [Due 2023-09-29]
- SITCOM-125 : LSSTCam reverification complete [Due 2023-10-03]
- SITCOM-127 : M2 coating decision [Due 2023-10-30]
- SITCOM-123 : LSSTCam Installed on TMA [Due 2023-12-26]
- LDM-503-16 : Ops rehearsal for data release processing #3 [Due 2024-01-18]
- DM-AP-17 : Solar System Processing pipeline available. [Due 2024-01-18]
- COMC-0140 : Begin Science Verification [Due 2024-03-15]
- DM-AP-16 : Full integration of the Alert Production system within the operational environment. [Due 2024-06-05]
Acronym | Description |
---|---|
AI | Artificial Intelligence |
AI&T | Assembly Integration & Test |
AP | Alert Production |
CCW | Camera Cable Wrap |
COMP | COMPlete |
ComCam | The commissioning camera is a single-raft, 9-CCD camera that will be installed in LSST during commissioning, before the final camera is ready. |
DM | Data Management |
EPO | Education and Public Outreach |
LDM | LSST Data Management (Document Handle) |
LSST | Legacy Survey of Space and Time (formerly Large Synoptic Survey Telescope) |
M1M3 | Primary Mirror Tertiary Mirror |
M2 | Secondary Mirror |
SC | Science Collaboration |
SITCOM | System Integration, Test and Commissioning |
SLAC | SLAC National Accelerator Laboratory |
TMA | Telescope Mount Assembly |