| Due | Name |
|---|---|
| 02-Dec-2022 | EPO Construction Finish |
| 16-Dec-2022 | Beneficial occupancy of the TMA |
| 16-Dec-2022 | TMA Handoff to Rubin |
| 12-May-2023 | COMP: Camera Pre-Ship Review at SLAC |
| 08-Nov-2023 | 3-Mirror Optical System Ready for Testing |
| 29-Nov-2023 | Engineering First Light w/ComCam |
| 21-Dec-2023 | Dome Complete |
| 14-Feb-2024 | Camera Ready for Full System AI&T |
| 19-Jul-2024 | System First Light |
| 14-Nov-2024 | Test report: Final Pipelines Delivery |
| 14-Nov-2024 | Mini-Survey 2 Complete |
| 21-Nov-2024 | Operation Readiness Review Complete |
Using October 2022 project controls data.