DueName
30-Sep-2022 EPO Construction Finish
21-Oct-2022 TMA Contract Complete
13-Mar-2023 COMP: Camera Pre-Ship Review at SLAC
29-Mar-2023 Dome Complete
20-Jul-2023 3-Mirror Optical System Ready for Testing
10-Aug-2023 Engineering First Light w/ComCam
11-Oct-2023 Camera Ready for Full System AI&T
14-Feb-2024 System First Light
11-Jun-2024 Test report: Final Pipelines Delivery
11-Jun-2024 Mini-Survey 2 Complete
18-Jun-2024 Operation Readiness Review Complete

Using May 2022 project controls data.