DueName Previously
02-Feb-2024 M1M3 Lift Test**Completed**
08-Feb-2024 TMA Final Testing Begins**Completed**
16-Feb-2024 M1M3 Glass Lift Prep**Completed**
19-Feb-2024 Pathfinder Testing starts**Completed**
20-Mar-2024 M1M3 Glass Installed**Completed**
25-Apr-2024 TMA Final Testing Complete**Completed**
29-Apr-2024 M1M3 Coating Begins**Completed**
29-Apr-2024 LSSTCam Arrival Allowed**Completed**
10-May-2024 LSSTCam Pack and Transport**Completed**
16-May-2024 LSSTCam Received @ Summit**Completed**
24-May-2024 ComCam Removed from TMA**Completed**
20-Jun-2024 M2 Cell Removed from TMA**Completed**
10-Jul-2024 M2 Glass Installed**Completed**
01-Aug-2024 M2 Glass on TMA18-Jul-2024
09-Aug-2024 ComCam Installed on TMA29-Jul-2024
15-Aug-2024 LSSTCam Reverification Start15-Jul-2024
17-Sep-2024 M1M3 Glass on TMA16-Sep-2024
18-Sep-2024 ComCam First Photon17-Sep-2024
22-Oct-2024 LSSTCam Reverification End19-Sep-2024
12-Nov-2024 ComCam off Sky11-Nov-2024
19-Nov-2024 ComCam off TMA18-Nov-2024
03-Dec-2024 LSSTCam on Top End Assembly02-Dec-2024
17-Dec-2024 LSSTCam L3 Checkout Done16-Dec-2024
01-Jan-2025 LSSTCam on TMA31-Dec-2024
08-Jan-2025 TMA Aligned07-Jan-2025
25-Feb-2025 Rubin First Photon24-Feb-2025
13-Mar-2025 TMA Pointing Models Complete13-Mar-2025
10-Apr-2025 TMA AOS Ready09-Apr-2025
16-May-2025 Rubin First Light15-May-2025
10-Jul-2025 Rubin SV1 Start09-Jul-2025
10-Jul-2025 Rubin SV2 Start09-Jul-2025
06-Aug-2025 Rubin Eng Prep for OPS Start05-Aug-2025
13-Aug-2025 Rubin Operations Readiness Review12-Aug-2025

Using July 2024 project controls data. This compares to June 2024.