DueName
30-Sep-2022 EPO Construction Finish (Completed 30-Sep-2022)
17-Mar-2023 TMA Handoff to Rubin
08-Aug-2023 COMP: Camera Pre-Ship Review at SLAC
01-Mar-2024 Camera Ready for Full System AI&T
18-Apr-2024 Dome Complete
19-Apr-2024 3-Mirror Optical System Ready for Testing
02-Sep-2024 System First Light
27-Dec-2024 Test report: Final Pipelines Delivery
27-Dec-2024 COMP: Science Validation Surveys Complete
03-Jan-2025 Operation Readiness Review Complete

Using February 2023 project controls data.