Due | Name |
---|---|
30-Sep-2022 | EPO Construction Finish (Completed 30-Sep-2022) |
03-Apr-2023 | TMA Handoff to Rubin |
01-Sep-2023 | COMP: Camera Pre-Ship Review at SLAC |
20-Mar-2024 | Dome Complete |
22-Apr-2024 | Camera Ready for Full System AI&T |
23-May-2024 | 3-Mirror Optical System Ready for Testing |
15-Jul-2024 | LSSTCam Ready for On Sky (First Photon) |
23-Oct-2024 | System First Light with LSSTCam |
18-Feb-2025 | Test report: Final Pipelines Delivery |
18-Feb-2025 | COMP: Science Validation Surveys Complete |
25-Feb-2025 | Operation Readiness Review Complete |
Using March 2023 project controls data.