| Due | Name |
|---|---|
| 30-Sep-2022 | EPO Construction Finish (Completed 30-Sep-2022) |
| 02-May-2023 | TMA Handoff to Rubin |
| 22-Sep-2023 | COMP: Camera Pre-Ship Review at SLAC |
| 23-Apr-2024 | Camera Ready for Full System AI&T |
| 26-Apr-2024 | Dome Complete |
| 08-May-2024 | 3-Mirror Optical System Ready for Testing |
| 16-Jul-2024 | LSSTCam Ready for On Sky (First Photon) |
| 24-Oct-2024 | System First Light with LSSTCam |
| 19-Feb-2025 | Test report: Final Pipelines Delivery |
| 19-Feb-2025 | COMP: Science Validation Surveys Complete |
| 26-Feb-2025 | Operation Readiness Review Complete |
Using April 2023 project controls data.