Provenance¶
This document was generated based on the contents of the lsst-dm/milestones repository, version a6a17673, dated 2023-06-12. This corresponds to the status recorded in the project controls system for April 2023.
Top milestones¶
- 2022-09-30 : EPO Construction Finish (EPOC285) Completed 2022-09-30
 - 2023-05-02 : TMA Handoff to Rubin (T&SC-0400-1730)
 - 2023-09-22 : COMP: Camera Pre-Ship Review at SLAC (CAMM8090)
 - 2024-04-23 : Camera Ready for Full System AI&T (COMC-060200-20930)
 - 2024-04-26 : Dome Complete (T&SC-0400-0950)
 - 2024-05-08 : 3-Mirror Optical System Ready for Testing (T&SC-1100-0400)
 - 2024-07-16 : LSSTCam Ready for On Sky (First Photon) (SITCOM-122)
 - 2024-10-24 : System First Light with LSSTCam (LSST-1520)
 - 2025-02-19 : Test report: Final Pipelines Delivery (LDM-503-17a)
 - 2025-02-19 : COMP: Science Validation Surveys Complete (COMC-0654-0430)
 - 2025-02-26 : Operation Readiness Review Complete (SITCOM-130)
 
A public HTML version for embedding is here.
Supporting milestones¶
- 2020-12-31 : ComCam Ops Readiness (LDM-503-11a) Completed 2020-12-31
 - 2022-09-30 : User Interfaces Complete (EPO-M6) Completed 2022-09-30
 - 2022-09-30 : Citizen Science Commissioning Project running via LSST infrastructure Complete (EPOC304) Completed 2022-09-30
 - 2022-12-01 : Camera support asmy w/ComCam+PF+Int#1+CCW Installed on Telescope (SITCOM-92) Completed 2022-12-01
 - 2023-02-28 : Ops rehearsal for data release processing #1 (LDM-503-13) Completed 2023-02-28
 - 2023-05-22 : COMP: Camera Ready for Verification Testing (ITC00475_COM)
 - 2023-05-31 : OCS Available on Summit (DM-35987)
 - 2023-05-31 : TCS Demonstrated (DM-35989)
 - 2023-06-07 : TMA safe for transition to M1M3 glass mirror (SITCOM-102)
 - 2023-07-20 : M1M3 cell+Surrogate Dynamic Testing on TMA done (SITCOM-97)
 - 2023-09-07 : ComCam + PF re-Installed on TMA (SITCOM-105)
 - 2023-10-13 : LSSTCam Received @ Summit (SUMMIT-2976)
 - 2023-10-26 : Love Contract Complete (LSST4820)
 - 2023-12-28 : M2 Software demonstrated (DM-35988)
 - 2024-01-29 : COMP: TMA Refrigeration Tests Complete (SUMMIT-3023)
 - 2024-03-27 : M2 coating decision (SITCOM-127)
 - 2024-03-27 : M2 Glass installed on Cell (SITCOM-104)
 - 2024-04-03 : Completion of the Scheduler (DM-27734)
 - 2024-04-11 : M2 Installed on Telescope (T&SC-1100-0300)
 - 2024-04-23 : LSSTCam reverification complete (SITCOM-125)
 - 2024-05-08 : M1M3 installed on the TMA (SITCOM-110)
 - 2024-05-22 : LSSTCam Installed on TMA (SITCOM-123)
 - 2024-07-09 : LSSTCam Cold (New1135)
 - 2024-08-01 : Full focal plane readout complete (New1110)
 - 2024-08-22 : Telescope Aligned (New1165)
 - 2024-10-24 : Solar System Processing pipeline available. (DM-AP-17)
 - 2024-10-24 : Initial Optical testing on TMA complete (SITCOM-116)
 - 2024-11-29 : Start SV Data Collection (COMC-0140)
 - 2025-02-19 : Full integration of the Alert Production system within the operational environment. (DM-AP-16)
 - 2025-02-26 : Ops rehearsal for data release processing #3 (LDM-503-16)
 
Download the PDF of this Block Schedule here.
| Acronym | Description | 
|---|---|
| AI | Artificial Intelligence | 
| AI&T | Assembly Integration & Test | 
| AP | Alert Production | 
| CCW | Camera Cable Wrap | 
| COMP | COMPlete | 
| ComCam | The commissioning camera is a single-raft, 9-CCD camera that will be installed in LSST during commissioning, before the final camera is ready. | 
| DM | Data Management | 
| EPO | Education and Public Outreach | 
| LDM | LSST Data Management (Document Handle) | 
| LSST | Legacy Survey of Space and Time (formerly Large Synoptic Survey Telescope) | 
| M1M3 | Primary Mirror Tertiary Mirror | 
| M2 | Secondary Mirror | 
| SC | Science Collaboration | 
| SITCOM | System Integration, Test and Commissioning | 
| SLAC | SLAC National Accelerator Laboratory | 
| TMA | Telescope Mount Assembly |