| Due | Name |
|---|---|
| 29-Sep-2022 | TMA Contract Complete |
| 30-Sep-2022 | EPO Construction Finish |
| 20-Mar-2023 | COMP: Camera Pre-Ship Review at SLAC |
| 28-Mar-2023 | Dome Complete |
| 17-May-2023 | 3-Mirror Optical System Ready for Testing |
| 19-Jul-2023 | Engineering First Light w/ComCam |
| 05-Sep-2023 | Camera Ready for Full System AI&T |
| 14-Feb-2024 | System First Light |
| 11-Jun-2024 | Test report: Final Pipelines Delivery |
| 11-Jun-2024 | Mini-Survey 2 Complete |
| 18-Jun-2024 | Operation Readiness Review Complete |
Using June 2022 project controls data.