DueName
02-Nov-2022 TMA Contract Complete
02-Dec-2022 EPO Construction Finish
29-Mar-2023 Dome Complete
01-May-2023 COMP: Camera Pre-Ship Review at SLAC
14-Jun-2023 3-Mirror Optical System Ready for Testing
20-Jul-2023 Engineering First Light w/ComCam
17-Oct-2023 Camera Ready for Full System AI&T
14-Mar-2024 System First Light
10-Jul-2024 Test report: Final Pipelines Delivery
10-Jul-2024 Mini-Survey 2 Complete
17-Jul-2024 Operation Readiness Review Complete

Using August 2022 project controls data.