Due | Name |
---|---|
30-Sep-2022 | EPO Construction Finish (Completed 30-Sep-2022) |
31-Mar-2023 | TMA Handoff to Rubin (Completed 31-Mar-2023) |
20-Oct-2023 | COMP: Camera Pre-Ship Review at SLAC |
29-Apr-2024 | Dome Complete |
30-Apr-2024 | Camera Ready for Full System AI&T |
13-Jun-2024 | 3-Mirror Optical System Ready for Testing |
24-Jul-2024 | LSSTCam Ready for On Sky (First Photon) |
01-Nov-2024 | System First Light with LSSTCam |
27-Feb-2025 | Test report: Final Pipelines Delivery |
27-Feb-2025 | COMP: Science Validation Surveys Complete |
06-Mar-2025 | Operation Readiness Review Complete |
Using June 2023 project controls data.