DueName Previously
02-Feb-2024 M1M3 Lift Test**Completed**
08-Feb-2024 TMA Final Testing Begins**Completed**
16-Feb-2024 M1M3 Glass Lift Prep**Completed**
19-Feb-2024 Pathfinder Testing starts**Completed**
20-Mar-2024 M1M3 Glass Installed**Completed**
30-Apr-2024 TMA Final Testing Complete2024-03-01
07-May-2024 M2 Cell Removed from TMA2024-05-09
21-May-2024 M1M3 Coating Begins2024-04-10
22-May-2024 LSSTCam Arrival Allowed2024-04-11
31-May-2024 LSSTCam Received @ Summit2024-05-22
14-Jun-2024 ComCam Removed from TMA2024-04-08
14-Jun-2024 LSSTCam Pack and Transport2024-04-15
05-Jul-2024 M2 Glass Installed2024-05-20
19-Jul-2024 M2 Glass on TMA2024-07-16
30-Jul-2024 ComCam Installed on TMA2024-07-25
06-Aug-2024 LSSTCam Reverification Start2024-08-08
13-Aug-2024 M1M3 Glass on TMA2024-07-12
14-Aug-2024 ComCam First Photon2024-07-26
08-Oct-2024 ComCam off Sky2024-09-19
11-Oct-2024 LSSTCam Reverification End2024-10-15
15-Oct-2024 ComCam off TMA2024-09-26
29-Oct-2024 LSSTCam on Top End Assembly2024-10-29
12-Nov-2024 LSSTCam L3 Checkout Done2024-11-12
27-Nov-2024 LSSTCam on TMA2024-11-26
04-Dec-2024 TMA Aligned2024-12-04
21-Jan-2025 Rubin First Photon2025-01-21
07-Feb-2025 TMA Pointing Models Complete2025-02-07
06-Mar-2025 TMA AOS Ready2025-03-06
11-Apr-2025 Rubin First Light2025-04-11
05-Jun-2025 Rubin SV1 Start2025-06-05
05-Jun-2025 Rubin SV2 Start2025-06-05
02-Jul-2025 Rubin Eng Prep for OPS Start2025-07-02
09-Jul-2025 Rubin Operations Readiness Review2025-07-09

Using March 2024 project controls data. This compares to February 2024.