DueName
30-Sep-2022 EPO Construction Finish (Completed 30-Sep-2022)
17-Mar-2023 TMA Handoff to Rubin
02-Aug-2023 COMP: Camera Pre-Ship Review at SLAC
26-Feb-2024 Camera Ready for Full System AI&T
15-Apr-2024 3-Mirror Optical System Ready for Testing
18-Apr-2024 Dome Complete
27-Aug-2024 System First Light
23-Dec-2024 Test report: Final Pipelines Delivery
23-Dec-2024 COMP: Science Validation Surveys Complete
30-Dec-2024 Operation Readiness Review Complete

Using February 2023 project controls data.