DueName Previously
02-Feb-2024 M1M3 Lift Test**Completed**
08-Feb-2024 TMA Final Testing Begins**Completed**
16-Feb-2024 M1M3 Glass Lift Prep**Completed**
19-Feb-2024 Pathfinder Testing starts**Completed**
20-Mar-2024 M1M3 Glass Installed**Completed**
01-Apr-2024 TMA Final Testing Complete2024-03-01
24-Apr-2024 M1M3 Coating Begins2024-04-10
24-Apr-2024 LSSTCam Arrival Allowed2024-04-11
07-May-2024 M2 Cell Removed from TMA2024-05-09
15-May-2024 LSSTCam Received @ Summit2024-05-22
29-May-2024 ComCam Removed from TMA2024-04-08
29-May-2024 LSSTCam Pack and Transport2024-04-15
19-Jun-2024 M2 Glass Installed2024-05-20
03-Jul-2024 M2 Glass on TMA2024-07-16
12-Jul-2024 ComCam Installed on TMA2024-07-25
19-Jul-2024 LSSTCam Reverification Start2024-07-26
26-Jul-2024 M1M3 Glass on TMA2024-07-12
29-Jul-2024 ComCam First Photon2024-07-26
20-Sep-2024 ComCam off Sky2024-09-19
25-Sep-2024 LSSTCam Reverification End2024-10-02
27-Sep-2024 ComCam off TMA2024-09-26
11-Oct-2024 LSSTCam on Top End Assembly2024-10-16
25-Oct-2024 LSSTCam L3 Checkout Done2024-10-30
11-Nov-2024 LSSTCam on TMA2024-11-13
18-Nov-2024 TMA Aligned2024-11-21
03-Jan-2025 Rubin First Photon2025-01-08
22-Jan-2025 TMA Pointing Models Complete2025-01-27
18-Feb-2025 TMA AOS Ready2025-02-21
26-Mar-2025 Rubin First Light2025-03-31
20-May-2025 Rubin SV1 Start2025-05-23
20-May-2025 Rubin SV2 Start2025-05-23
16-Jun-2025 Rubin Eng Prep for OPS Start2025-06-19
23-Jun-2025 Rubin Operations Readiness Review2025-06-26

Using March 2024 project controls data. This compares to February 2024.