03-Oct-2022 DELETE Engineering First Light w/ComCam
16-Jan-2023 TMA Contract Complete
16-Jan-2023 TMA Handoff to Rubin
12-May-2023 COMP: Camera Pre-Ship Review at SLAC
29-Sep-2023 EPO Construction Finish
05-Dec-2023 Camera Ready for Full System AI&T
21-Dec-2023 Dome Complete
15-Mar-2024 3-Mirror Optical System Ready for Testing
15-Jul-2024 System First Light
08-Nov-2024 Test report: Final Pipelines Delivery
08-Nov-2024 Mini-Survey 2 Complete
15-Nov-2024 Operation Readiness Review Complete

Using October 2022 project controls data.