| Due | Name | 
|---|---|
| 30-Sep-2022 | EPO Construction Finish (Completed 30-Sep-2022) | 
| 31-Jan-2023 | TMA Handoff to Rubin | 
| 19-May-2023 | COMP: Camera Pre-Ship Review at SLAC | 
| 13-Dec-2023 | Camera Ready for Full System AI&T | 
| 21-Dec-2023 | Dome Complete | 
| 11-Mar-2024 | 3-Mirror Optical System Ready for Testing | 
| 16-Jul-2024 | System First Light | 
| 11-Nov-2024 | Test report: Final Pipelines Delivery | 
| 11-Nov-2024 | COMP: Science Validation Surveys Complete | 
| 18-Nov-2024 | Operation Readiness Review Complete | 
Using November 2022 project controls data.