DueName
30-Sep-2022 EPO Construction Finish (Completed 30-Sep-2022)
31-Jan-2023 TMA Handoff to Rubin
19-May-2023 COMP: Camera Pre-Ship Review at SLAC
13-Dec-2023 Camera Ready for Full System AI&T
21-Dec-2023 Dome Complete
11-Mar-2024 3-Mirror Optical System Ready for Testing
16-Jul-2024 System First Light
11-Nov-2024 Test report: Final Pipelines Delivery
11-Nov-2024 COMP: Science Validation Surveys Complete
18-Nov-2024 Operation Readiness Review Complete

Using November 2022 project controls data.