DueName Previously
02-Feb-2024 M1M3 Lift Test**Completed**
08-Feb-2024 TMA Final Testing Begins**Completed**
16-Feb-2024 M1M3 Glass Lift Prep**Completed**
19-Feb-2024 Pathfinder Testing starts**Completed**
20-Mar-2024 M1M3 Glass Installed**Completed**
25-Apr-2024 TMA Final Testing Complete**Completed**
29-Apr-2024 M1M3 Coating Begins**Completed**
29-Apr-2024 LSSTCam Arrival Allowed**Completed**
10-May-2024 LSSTCam Pack and Transport**Completed**
16-May-2024 LSSTCam Received @ Summit**Completed**
24-May-2024 ComCam Removed from TMA**Completed**
07-Jun-2024 M2 Cell Removed from TMA22-May-2024
28-Jun-2024 M2 Glass Installed12-Jun-2024
12-Jul-2024 M2 Glass on TMA26-Jun-2024
15-Jul-2024 LSSTCam Reverification Start19-Jul-2024
23-Jul-2024 ComCam Installed on TMA05-Jul-2024
07-Aug-2024 M1M3 Glass on TMA31-Jul-2024
08-Aug-2024 ComCam First Photon01-Aug-2024
19-Sep-2024 LSSTCam Reverification End25-Sep-2024
02-Oct-2024 ComCam off Sky25-Sep-2024
09-Oct-2024 ComCam off TMA02-Oct-2024
23-Oct-2024 LSSTCam on Top End Assembly16-Oct-2024
06-Nov-2024 LSSTCam L3 Checkout Done30-Oct-2024
21-Nov-2024 LSSTCam on TMA14-Nov-2024
28-Nov-2024 TMA Aligned21-Nov-2024
15-Jan-2025 Rubin First Photon08-Jan-2025
03-Feb-2025 TMA Pointing Models Complete27-Jan-2025
28-Feb-2025 TMA AOS Ready21-Feb-2025
07-Apr-2025 Rubin First Light31-Mar-2025
30-May-2025 Rubin SV1 Start23-May-2025
30-May-2025 Rubin SV2 Start23-May-2025
26-Jun-2025 Rubin Eng Prep for OPS Start19-Jun-2025
03-Jul-2025 Rubin Operations Readiness Review26-Jun-2025

Using May 2024 project controls data. This compares to April 2024.