Due | Name |
---|---|
13-May-2022 | TMA Contract Complete |
27-Jul-2022 | COMP: Camera Pre-Ship Review at SLAC |
29-Jul-2022 | Dome Complete |
30-Sep-2022 | EPO Construction Finish |
13-Feb-2023 | 3-Mirror Optical System Ready for Testing |
10-Apr-2023 | Engineering First Light w/ComCam |
04-May-2023 | Camera Ready for Full System AI&T |
01-Sep-2023 | System First Light |
05-Jan-2024 | Test report: Final Pipelines Delivery |
05-Jan-2024 | Mini-Survey 2 Complete |
12-Jan-2024 | Operation Readiness Review Complete |
Using July 2022 project controls data.