Due | Name |
---|---|
14-Oct-2022 | TMA Contract Complete |
27-Feb-2023 | COMP: Camera Pre-Ship Review at SLAC |
29-Mar-2023 | Dome Complete |
13-Jul-2023 | 3-Mirror Optical System Ready for Testing |
31-Aug-2023 | EPO Construction Finish |
07-Sep-2023 | Engineering First Light w/ComCam |
03-Oct-2023 | Camera Ready for Full System AI&T |
18-Jan-2024 | System First Light |
05-Jun-2024 | Test report: Final Pipelines Delivery |
05-Jun-2024 | Mini-Survey 2 Complete |
12-Jun-2024 | Operation Readiness Review Complete |
Using May 2022 project controls data.