DueName
30-Sep-2022 EPO Construction Finish (Completed 30-Sep-2022)
28-Feb-2023 TMA Handoff to Rubin
21-Jun-2023 COMP: Camera Pre-Ship Review at SLAC
04-Apr-2024 Camera Ready for Full System AI&T
18-Apr-2024 Dome Complete
20-May-2024 3-Mirror Optical System Ready for Testing
28-Jun-2024 LSSTCam Ready for On Sky (First Photon)
08-Oct-2024 System First Light
03-Feb-2025 Test report: Final Pipelines Delivery
03-Feb-2025 COMP: Science Validation Surveys Complete
10-Feb-2025 Operation Readiness Review Complete

Using March 2023 project controls data.